ES Questions: Setting Up the Work Site
Authority from the PICOP, work-site marker boards, engineering trains and the details you record and read back.
Updated 17 November 2026 for the rules in force now and the 5 December change
Key rules
See all 20 key rulesContact the PICOP and state the published possession reference, if there is one.
GERT8000-HB12 Duties of the ES in a possession, Setting up the work site
Confirm with the PICOP the line and exact mileage of each work-site marker board (WSMB).
GERT8000-HB12 Duties of the ES in a possession, Setting up the work site
Confirm with the PICOP whether the work site is to be taken around one or more trains.
GERT8000-HB12 Duties of the ES in a possession, Setting up the work site
Confirm with the PICOP the arrangements for every level crossing within the work site.
GERT8000-HB12 Duties of the ES in a possession, Setting up the work site
Wait for the PICOP to authorise you to set up the work site before allowing WSMB placement duties to start.
GERT8000-HB12 Duties of the ES in a possession, Setting up the work site
The PICOP may authorise you to set up the work site after the signaller has authorised possession protection to be placed.
GERT8000-HB11 Duties of the person in charge of the possession, Arranging the possession protection
After the PICOP authorises setup, you may allow an isolation COSS to carry out AC method isolation duties.
GERT8000-HB12 Duties of the ES in a possession, Setting up the work site
Before an isolation COSS starts work, give them a work-site briefing and record the required information in Appendix B of the RT3199.
GERT8000-HB12 Duties of the ES in a possession, Setting up the work site
Do not allow other work within the work site until the PICOP tells you the work site has been granted.
GERT8000-HB12 Duties of the ES in a possession, Setting up the work site
Before proceeding with setup or extension around engineering trains, the PICOP must confirm that every train concerned is at its specified signal, block marker or flexible train arrival point.
GERT8000-HB12 Duties of the ES in a possession, Setting up or extending the work site
Do not allow those trains to move again until the WSMBs are in place and all necessary work-site arrangements have been made.
GERT8000-HB12 Duties of the ES in a possession, Setting up or extending the work site
Before authorising an engineering train around which the work site is being set up or extended to move, tell its driver that the possession has been granted.
GERT8000-HB12 Duties of the ES in a possession, Setting up or extending the work site
Sample questions
1. You are the ES waiting to set up a work site. Who authorises you to set it up?
- The PICOP
- The signaller
- The COSS
- The train driver
Answer: A. The PICOP
The PICOP authorises each ES to set up their work site. Wait for that authorisation before setting it up.
- The signaller: The signaller gives the PICOP permission to arrange protection, not the ES authorisation.
- The COSS: The COSS does not authorise the ES to set up the work site.
- The train driver: The train driver does not authorise the ES to set up the work site.
Source: GERT8000-HB11 Duties of the person in charge of the possession (Iss 11, Arranging the possession protection
2. The PICOP is arranging possession protection. What will the signaller confirm when the line is clear, apart from any permitted trains at a stand?
- The possession protection has been placed and checked
- The ES has set up the work site limits
- The signals are at danger or the routes closed
- The work-site marker boards have been placed
Answer: C. The signals are at danger or the routes closed
The signaller tells the PICOP when signals leading to the possession are at danger or the routes are closed. The PICOP can then complete the relevant part of the possession arrangements form.
- The possession protection has been placed and checked: This confirmation precedes arranging the possession protection.
- The ES has set up the work site limits: The signaller's confirmation is not that the work site has been set up.
- The work-site marker boards have been placed: Marker boards may be placed later, following the appropriate authorisation.
Source: GERT8000-HB11 Duties of the person in charge of the possession (Iss 11, Arranging the possession protection
3. You tell the PICOP that the WSMBs at both ends of your work site are in position. What should happen next?
- You authorise work and then send the PICOP the RT3199 details.
- The PICOP removes the WSMBs and completes the RT3198.
- The PICOP dictates the details for you to enter on the RT3199.
- You dictate the details for the PICOP to enter on your RT3199.
Answer: C. The PICOP dictates the details for you to enter on the RT3199.
Once both WSMBs are in position, the PICOP dictates the details for the ES to enter on the RT3199. The ES then reads the details back.
- You authorise work and then send the PICOP the RT3199 details: The PICOP authorises work after checking the details are in order.
- The PICOP removes the WSMBs and completes the RT3198: The WSMBs remain the indication of the work site.
- You dictate the details for the PICOP to enter on your RT3199: The PICOP dictates the details to the ES, not the other way round.
Source: GERT8000-HB11 Duties of the person in charge of the possession (Iss 11, Allowing work to start inside the work / 6.4 When a work site is suspended
4. A level crossing is within your work site. What must the PICOP include when dictating the RT3199 details to you?
- Only the crossing’s location within the work site.
- The arrangements made for that level crossing.
- Only the name of the crossing attendant.
- The arrangements for crossings outside the work site.
Answer: B. The arrangements made for that level crossing.
The details dictated for the RT3199 must include the arrangements made for each level crossing within the work site. This ensures those arrangements form part of the certificate details.
- Only the crossing’s location within the work site: The crossing arrangements must be included, not just its location.
- Only the name of the crossing attendant: The requirement is to include the arrangements made for the crossing.
- The arrangements for crossings outside the work site: The specified requirement concerns each crossing within the work site.
Source: GERT8000-HB11 Duties of the person in charge of the possession (Iss 11, Allowing work to start inside the work / 6.4 When a work site is suspended
5. You have entered the dictated details on the RT3199 and read them back. When may the PICOP give you their full initials and authorise work to start?
- As soon as you confirm that the details have been entered.
- When the PICOP is satisfied that all details are in order.
- When the PICOP has recorded the details on the RT3198.
- As soon as you have completed the read-back.
Answer: B. When the PICOP is satisfied that all details are in order.
The PICOP must be satisfied that all details are in order for work to start before giving full initials and authorisation. A completed read-back alone does not establish that the PICOP is satisfied.
- As soon as you confirm that the details have been entered: Entering the details alone does not establish that they are in order.
- When the PICOP has recorded the details on the RT3198: The PICOP must be satisfied that all details are in order.
- As soon as you have completed the read-back: The PICOP must be satisfied with the details after the read-back.
Source: GERT8000-HB11 Duties of the person in charge of the possession (Iss 11, Allowing work to start inside the work / 6.4 When a work site is suspended