Kerrie Callaghan Project Management English 3 cards

Cards in this deck (3)

  1. 1What is the critical path?The path through the network with zero floats.
  2. 2What is an activities float?The difference between its earliest and latest finish dates
  3. 3What is float a measure of?How much the start or completion of an activity may be delayed without affecting the end date of a project

Information

Description
Project Management Flashcards on CPM, created by Kerrie Callaghan on 13/05/2018.