Exams · US

PMP practice questions: Continuous improvement

Learning from the work and improving how the project is run.

8 questions · 10 key rules

Updated 17 November 2026 for the 2026 PMP exam content outline

Key facts

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Continuous improvement1. A hybrid healthcare project is planning its next phase. A similar completed project recorded lessons about delays in getting user feedback. What should the project manager do next?
    1. Wait until the next phase ends to review the recorded lessons.
    2. Ask the sponsor to approve every lesson before the team reviews it.
    3. Copy all actions from the earlier project into the current plan.
    4. Review the lessons with the team and use applicable actions in planning.
    Show answer and explanation

    Answer: D. Review the lessons with the team and use applicable actions in planning.

    The team should consider relevant past experience while planning and adapt useful actions to the current project. This supports Business Environment, Task 6: Continuous improvement.

    Why the others are wrong

    • Wait until the next phase ends to review the recorded lessons: Waiting loses an opportunity to prevent similar delays.
    • Ask the sponsor to approve every lesson before the team reviews it: The sponsor need not approve lessons before the team reviews them.
    • Copy all actions from the earlier project into the current plan: Not every action from another project will fit the current situation.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 6: Continuous improvement

  2. Continuous improvement2. During a predictive construction project, the team identifies a better way to coordinate inspections with a supplier. Several inspections remain. What should the project manager do next?
    1. Save the idea for the final project review without changing current work.
    2. Ask the team to assess the idea and apply it where appropriate.
    3. Require the supplier to adopt the idea immediately without team review.
    4. Escalate the idea to the sponsor before discussing it with the team.
    Show answer and explanation

    Answer: B. Ask the team to assess the idea and apply it where appropriate.

    The team can assess and use a lesson during the project rather than waiting until closure. This supports Business Environment, Task 6: Continuous improvement.

    Why the others are wrong

    • Save the idea for the final project review without changing current work: Waiting until closure misses a chance to improve remaining inspections.
    • Require the supplier to adopt the idea immediately without team review: Immediate adoption skips assessment of the idea and its effects.
    • Escalate the idea to the sponsor before discussing it with the team: Escalation is premature when the team can first assess the idea.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 6: Continuous improvement

  3. Continuous improvement3. A software team recorded lessons after several iterations, but the same handoff delays keep recurring. What should the project manager do? Choose two.
    1. Work with the team to identify which lessons address the delays.
    2. Assign ownership for an agreed improvement and review its results.
    3. Close the lessons once they have been recorded for future teams.
    4. Ask the sponsor to replace the team members involved in handoffs.
    5. Continue the current process until the project is complete.
    Show answer and explanation

    Answer: A. Work with the team to identify which lessons address the delays., B. Assign ownership for an agreed improvement and review its results.

    Identifying relevant lessons and following through on an improvement turns recorded experience into action. Reviewing the result supports Business Environment, Task 6: Continuous improvement.

    Why the others are wrong

    • Close the lessons once they have been recorded for future teams: Recording a lesson alone does not resolve the recurring delay.
    • Ask the sponsor to replace the team members involved in handoffs: Replacing team members is premature without understanding the delay.
    • Continue the current process until the project is complete: Waiting allows a known problem to continue.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 6: Continuous improvement

  4. Continuous improvement4. A public-sector project is closing after successfully improving stakeholder engagement. Another team is beginning a similar hybrid project. What should the project manager do to help that team use the experience?
    1. Share the relevant lessons and discuss their context with the new team.
    2. Send the new team the final schedule without further context.
    3. Ask the new team to repeat the same engagement plan unchanged.
    4. Wait until the new team reports an engagement problem before sharing.
    Show answer and explanation

    Answer: A. Share the relevant lessons and discuss their context with the new team.

    Sharing lessons with their context helps the new team judge which practices fit its stakeholders. This supports Business Environment, Task 6: Continuous improvement.

    Why the others are wrong

    • Send the new team the final schedule without further context: A schedule alone may not explain what improved engagement or why.
    • Ask the new team to repeat the same engagement plan unchanged: An unchanged plan may not fit the new project's stakeholders.
    • Wait until the new team reports an engagement problem before sharing: Waiting may let preventable engagement problems develop.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 6: Continuous improvement

Sign up free

Other PMP topics

GoConqr Original. Practice questions written with AI from the PMI 2026 PMP Examination Content Outline and settled project-management practice, each checked by a separate AI review. They are single- and multiple-response only: case sets, drag-and-drop, hotspot and pull-down items are not reproduced. Think a question is wrong? Use "Report" under it.

Independent study resource. Not affiliated with PMI. PMP and PMI are marks of the Project Management Institute.

© Visual Maths Resources Ltd

Feedback

What is it about?