PMP practice questions: Continuous improvement
Learning from the work and improving how the project is run.
Updated 17 November 2026 for the 2026 PMP exam content outline
Key facts
Review relevant lessons learned from previous work when planning and adapting the project.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 6: Continuous improvement
Capture lessons learned throughout the project, including effective practices, problems, causes, and recommended actions.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 6: Continuous improvement
Discuss lessons with the team and stakeholders, then apply relevant findings to current and future work.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 6: Continuous improvement
Use retrospectives or other reviews at suitable intervals to identify improvements in predictive, adaptive/agile, and hybrid projects.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 6: Continuous improvement
Prioritize improvement opportunities by their expected value, feasibility, and impact.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 6: Continuous improvement
Assign ownership and a target date to agreed improvement actions, and track their completion.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 6: Continuous improvement
Measure improvement results and adjust the process when the intended benefits are not achieved.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 6: Continuous improvement
Follow applicable governance and approval procedures when updating continuous improvement processes.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 6: Continuous improvement
Update organizational process assets (OPAs), such as templates, procedures, and lessons learned repositories, with validated improvements.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 6: Continuous improvement
Make updated OPAs accessible to relevant teams and communicate changes so they can be used consistently.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 6: Continuous improvement
Sample questions
1. A hybrid healthcare project is planning its next phase. A similar completed project recorded lessons about delays in getting user feedback. What should the project manager do next?
- Wait until the next phase ends to review the recorded lessons.
- Ask the sponsor to approve every lesson before the team reviews it.
- Copy all actions from the earlier project into the current plan.
- Review the lessons with the team and use applicable actions in planning.
Answer: D. Review the lessons with the team and use applicable actions in planning.
The team should consider relevant past experience while planning and adapt useful actions to the current project. This supports Business Environment, Task 6: Continuous improvement.
- Wait until the next phase ends to review the recorded lessons: Waiting loses an opportunity to prevent similar delays.
- Ask the sponsor to approve every lesson before the team reviews it: The sponsor need not approve lessons before the team reviews them.
- Copy all actions from the earlier project into the current plan: Not every action from another project will fit the current situation.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 6: Continuous improvement
2. During a predictive construction project, the team identifies a better way to coordinate inspections with a supplier. Several inspections remain. What should the project manager do next?
- Save the idea for the final project review without changing current work.
- Ask the team to assess the idea and apply it where appropriate.
- Require the supplier to adopt the idea immediately without team review.
- Escalate the idea to the sponsor before discussing it with the team.
Answer: B. Ask the team to assess the idea and apply it where appropriate.
The team can assess and use a lesson during the project rather than waiting until closure. This supports Business Environment, Task 6: Continuous improvement.
- Save the idea for the final project review without changing current work: Waiting until closure misses a chance to improve remaining inspections.
- Require the supplier to adopt the idea immediately without team review: Immediate adoption skips assessment of the idea and its effects.
- Escalate the idea to the sponsor before discussing it with the team: Escalation is premature when the team can first assess the idea.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 6: Continuous improvement
3. A software team recorded lessons after several iterations, but the same handoff delays keep recurring. What should the project manager do? Choose two.
- Work with the team to identify which lessons address the delays.
- Assign ownership for an agreed improvement and review its results.
- Close the lessons once they have been recorded for future teams.
- Ask the sponsor to replace the team members involved in handoffs.
- Continue the current process until the project is complete.
Answer: A. Work with the team to identify which lessons address the delays., B. Assign ownership for an agreed improvement and review its results.
Identifying relevant lessons and following through on an improvement turns recorded experience into action. Reviewing the result supports Business Environment, Task 6: Continuous improvement.
- Close the lessons once they have been recorded for future teams: Recording a lesson alone does not resolve the recurring delay.
- Ask the sponsor to replace the team members involved in handoffs: Replacing team members is premature without understanding the delay.
- Continue the current process until the project is complete: Waiting allows a known problem to continue.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 6: Continuous improvement
4. A public-sector project is closing after successfully improving stakeholder engagement. Another team is beginning a similar hybrid project. What should the project manager do to help that team use the experience?
- Share the relevant lessons and discuss their context with the new team.
- Send the new team the final schedule without further context.
- Ask the new team to repeat the same engagement plan unchanged.
- Wait until the new team reports an engagement problem before sharing.
Answer: A. Share the relevant lessons and discuss their context with the new team.
Sharing lessons with their context helps the new team judge which practices fit its stakeholders. This supports Business Environment, Task 6: Continuous improvement.
- Send the new team the final schedule without further context: A schedule alone may not explain what improved engagement or why.
- Ask the new team to repeat the same engagement plan unchanged: An unchanged plan may not fit the new project's stakeholders.
- Wait until the new team reports an engagement problem before sharing: Waiting may let preventable engagement problems develop.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 6: Continuous improvement