PMP practice questions: Help ensure knowledge transfer
Sharing knowledge within the project and protecting confidential and sensitive information when you store or share it.
Updated 17 November 2026 for the 2026 PMP exam content outline
Key facts
Identify knowledge critical to delivering, operating, and supporting the project’s outcomes.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 7: Help ensure knowledge transfer
Identify who holds critical knowledge, who needs it, and when they need it.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 7: Help ensure knowledge transfer
Prioritize knowledge transfer where losing expertise would threaten project continuity or outcomes.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 7: Help ensure knowledge transfer
Gather existing knowledge from relevant people, project artifacts, and organizational process assets.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 7: Help ensure knowledge transfer
Capture lessons learned throughout the project rather than waiting until closure.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 7: Help ensure knowledge transfer
Transfer tacit knowledge through discussion, observation, mentoring, or hands-on practice.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 7: Help ensure knowledge transfer
Record useful knowledge in an accessible form and keep it current for its intended audience.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 7: Help ensure knowledge transfer
Protect confidential and sensitive information when storing or sharing knowledge.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 7: Help ensure knowledge transfer
Foster a safe environment where people can ask questions and share mistakes without blame.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 7: Help ensure knowledge transfer
Provide time and opportunities for knowledge sharing, including during team transitions and handoffs.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 7: Help ensure knowledge transfer
Confirm that recipients understand and can apply transferred knowledge.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 7: Help ensure knowledge transfer
Sample questions
1. On a predictive hospital project, the only engineer who understands a custom equipment interface plans to leave. Other team members have not worked with it. What should the project manager identify as a knowledge priority?
- The team's preferences for status reports
- The sponsor's preferred meeting schedule
- The engineer's knowledge of the custom interface
- The vendor's general marketing materials
Answer: C. The engineer's knowledge of the custom interface
The interface knowledge is critical because the project depends on it and only one person currently holds it. Identifying it early allows the team to plan for its transfer. This supports People, Task 7: Help ensure knowledge transfer.
- The team's preferences for status reports: Report preferences do not address the risk of losing essential technical knowledge.
- The sponsor's preferred meeting schedule: The sponsor's schedule is not the knowledge at risk.
- The vendor's general marketing materials: General marketing materials are unlikely to replace knowledge of the custom interface.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 7: Help ensure knowledge transfer
2. A software team uses a backlog to develop a payment feature. A specialist knows why certain transaction rules were chosen, but the reasons are not recorded. What should the project manager do next?
- Ask the team to postpone the payment feature
- Replace the rules with the latest team assumptions
- Escalate the missing rationale to the sponsor
- Identify the transaction-rule rationale as critical knowledge
Answer: D. Identify the transaction-rule rationale as critical knowledge
The rationale can help the team make informed changes without unintentionally undermining the payment rules. Identifying it as critical knowledge is the first step toward preserving it. This supports People, Task 7: Help ensure knowledge transfer.
- Ask the team to postpone the payment feature: Postponing the feature is premature before assessing the knowledge need.
- Replace the rules with the latest team assumptions: Replacing rules based on assumptions risks losing the reasons behind them.
- Escalate the missing rationale to the sponsor: Escalation is premature when the team can first identify the knowledge needed.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 7: Help ensure knowledge transfer
3. A hybrid public-sector project is preparing for a team transition. Several documents and specialists are available, but the team cannot transfer everything at once. How should the project manager prioritize knowledge?
- Select knowledge by its importance to upcoming work and risk of loss
- Select knowledge held by the most senior staff first
- Select knowledge that is easiest to document first
- Select knowledge from the most recently completed work first
Answer: A. Select knowledge by its importance to upcoming work and risk of loss
Knowledge needed for upcoming work is especially important when it could also be lost during the transition. Considering both factors helps the team focus limited transfer time on the greatest project needs. This supports People, Task 7: Help ensure knowledge transfer.
- Select knowledge held by the most senior staff first: Seniority alone does not show whether knowledge is critical.
- Select knowledge that is easiest to document first: Ease of documentation does not establish project importance.
- Select knowledge from the most recently completed work first: Recent work may be less important than knowledge needed for upcoming work.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 7: Help ensure knowledge transfer
4. A construction project is moving from design to implementation under an approved baseline. The delivery team understands the drawings but not why a key site constraint shaped the design. What should the project manager identify for transfer?
- The team's preferred format for progress updates
- The reasoning behind the design constraint and its effects
- The history of routine design meeting attendance
- The sequence used to number the drawings
Answer: B. The reasoning behind the design constraint and its effects
Understanding the constraint and its effects helps the delivery team make decisions that remain consistent with the design. The reasoning is therefore important knowledge for the transition. This supports People, Task 7: Help ensure knowledge transfer.
- The team's preferred format for progress updates: Update preferences do not explain the design constraint.
- The history of routine design meeting attendance: Meeting attendance does not provide the reasoning needed for delivery.
- The sequence used to number the drawings: Drawing numbering helps navigation but does not explain the constraint.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 7: Help ensure knowledge transfer