Exams · US

PMP practice questions: Evaluate project status

Measuring progress and reporting where the project stands.

11 questions · 10 key rules

Updated 17 November 2026 for the 2026 PMP exam content outline

Key facts

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Project status1. A predictive construction project has earned value of $80,000 and actual cost of $100,000. The project manager is preparing a cost status report. What is the cost performance index (CPI)?
    1. 0.20
    2. 0.80
    3. 1.20
    4. 1.25
    Show answer and explanation

    Answer: B. 0.80

    CPI is earned value divided by actual cost: $80,000 ÷ $100,000 = 0.80. This indicates that the project has earned $0.80 of planned value for each dollar spent; this supports Process, Task 9: Evaluate project status.

    Why the others are wrong

    • 0.20: 0.20 is the difference between the two values expressed as a ratio, not CPI.
    • 1.20: 1.20 does not result from the CPI formula.
    • 1.25: 1.25 reverses actual cost and earned value.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 9: Evaluate project status

  2. Project status2. A hybrid project involves several departments that may request changes to shared requirements. The team needs a consistent way to record and follow those requests. What should the project manager do next?
    1. Record each request only in meeting notes
    2. Create a change log suited to the project
    3. Ask each department to keep its own records
    4. Wait until the project closes to document changes
    Show answer and explanation

    Answer: B. Create a change log suited to the project

    A tailored change log gives the team a consistent way to track requests across departments. This supports Process, Task 9: Evaluate project status.

    Why the others are wrong

    • Record each request only in meeting notes: Meeting notes alone make requests harder to follow consistently.
    • Ask each department to keep its own records: Separate records can make it difficult to reconcile requests.
    • Wait until the project closes to document changes: Waiting until closure prevents the team from tracking requests as they arise.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 9: Evaluate project status

  3. Project status3. An adaptive product team uses a detailed status template designed for a large predictive project. Much of the information is duplicated in the backlog and is not used by stakeholders. What should the project manager do?
    1. Keep every template field to preserve consistency
    2. Stop reporting status because the backlog exists
    3. Agree on a leaner status artifact with stakeholders
    4. Create a separate report for every stakeholder
    Show answer and explanation

    Answer: C. Agree on a leaner status artifact with stakeholders

    Tailoring the status artifact to stakeholder needs can reduce duplication while preserving useful information. This supports Process, Task 9: Evaluate project status.

    Why the others are wrong

    • Keep every template field to preserve consistency: Keeping unused fields does not address unnecessary effort.
    • Stop reporting status because the backlog exists: The backlog alone may not meet all stakeholder status needs.
    • Create a separate report for every stakeholder: Separate reports for everyone may increase duplication.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 9: Evaluate project status

  4. Project status4. A predictive healthcare project has an issue log, but several resolved issues still appear open. The project manager is preparing for a status review. What should the project manager do next?
    1. Remove the resolved issues from the log.
    2. Send the unchanged log to the sponsor.
    3. Update and document the issues' current status.
    4. Create a separate log for each team member.
    Show answer and explanation

    Answer: C. Update and document the issues' current status.

    Updating the issue log gives the review an accurate record of current and resolved issues. This supports Process, Task 9: Evaluate project status.

    Why the others are wrong

    • Remove the resolved issues from the log: Removing entries loses the documented history of resolved issues.
    • Send the unchanged log to the sponsor: Sending an outdated log can misrepresent project status.
    • Create a separate log for each team member: Separate logs do not address the inaccurate status.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 9: Evaluate project status

Sign up free

Other PMP topics

GoConqr Original. Practice questions written with AI from the PMI 2026 PMP Examination Content Outline and settled project-management practice, each checked by a separate AI review. They are single- and multiple-response only: case sets, drag-and-drop, hotspot and pull-down items are not reproduced. Think a question is wrong? Use "Report" under it.