PMP practice questions: Evaluate project status
Measuring progress and reporting where the project stands.
Updated 17 November 2026 for the 2026 PMP exam content outline
Key facts
Choose measurable indicators that reflect project objectives, stakeholder information needs, and the delivery approach.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 9: Evaluate project status
Define each metric's data source, calculation, reporting frequency, and meaningful thresholds.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 9: Evaluate project status
Reconcile discrepancies between status data sources before drawing conclusions or reporting results.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 9: Evaluate project status
Select and tailor artifacts to the project's needs, delivery approach, governance, and stakeholder requirements.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 9: Evaluate project status
Assign responsibility for creating, reviewing, updating, and documenting project artifacts throughout the project.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 9: Evaluate project status
Keep current artifacts accessible to authorized stakeholders while protecting sensitive information and controlling versions.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 9: Evaluate project status
Assess progress against relevant plans, baselines, delivery goals, and acceptance criteria using reliable evidence.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 9: Evaluate project status
Measure and analyze metrics regularly, investigate trends and variances, and update metrics when project needs change.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 9: Evaluate project status
Communicate status, significant variances, risks, impediments, and needed decisions in a form and cadence suited to stakeholders.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 9: Evaluate project status
Continually assess whether artifact management supports accurate, timely, and accessible information, and improve it when necessary.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 9: Evaluate project status
Sample questions
1. A predictive construction project has earned value of $80,000 and actual cost of $100,000. The project manager is preparing a cost status report. What is the cost performance index (CPI)?
- 0.20
- 0.80
- 1.20
- 1.25
Answer: B. 0.80
CPI is earned value divided by actual cost: $80,000 ÷ $100,000 = 0.80. This indicates that the project has earned $0.80 of planned value for each dollar spent; this supports Process, Task 9: Evaluate project status.
- 0.20: 0.20 is the difference between the two values expressed as a ratio, not CPI.
- 1.20: 1.20 does not result from the CPI formula.
- 1.25: 1.25 reverses actual cost and earned value.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 9: Evaluate project status
2. A hybrid project involves several departments that may request changes to shared requirements. The team needs a consistent way to record and follow those requests. What should the project manager do next?
- Record each request only in meeting notes
- Create a change log suited to the project
- Ask each department to keep its own records
- Wait until the project closes to document changes
Answer: B. Create a change log suited to the project
A tailored change log gives the team a consistent way to track requests across departments. This supports Process, Task 9: Evaluate project status.
- Record each request only in meeting notes: Meeting notes alone make requests harder to follow consistently.
- Ask each department to keep its own records: Separate records can make it difficult to reconcile requests.
- Wait until the project closes to document changes: Waiting until closure prevents the team from tracking requests as they arise.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 9: Evaluate project status
3. An adaptive product team uses a detailed status template designed for a large predictive project. Much of the information is duplicated in the backlog and is not used by stakeholders. What should the project manager do?
- Keep every template field to preserve consistency
- Stop reporting status because the backlog exists
- Agree on a leaner status artifact with stakeholders
- Create a separate report for every stakeholder
Answer: C. Agree on a leaner status artifact with stakeholders
Tailoring the status artifact to stakeholder needs can reduce duplication while preserving useful information. This supports Process, Task 9: Evaluate project status.
- Keep every template field to preserve consistency: Keeping unused fields does not address unnecessary effort.
- Stop reporting status because the backlog exists: The backlog alone may not meet all stakeholder status needs.
- Create a separate report for every stakeholder: Separate reports for everyone may increase duplication.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 9: Evaluate project status
4. A predictive healthcare project has an issue log, but several resolved issues still appear open. The project manager is preparing for a status review. What should the project manager do next?
- Remove the resolved issues from the log.
- Send the unchanged log to the sponsor.
- Update and document the issues' current status.
- Create a separate log for each team member.
Answer: C. Update and document the issues' current status.
Updating the issue log gives the review an accurate record of current and resolved issues. This supports Process, Task 9: Evaluate project status.
- Remove the resolved issues from the log: Removing entries loses the documented history of resolved issues.
- Send the unchanged log to the sponsor: Sending an outdated log can misrepresent project status.
- Create a separate log for each team member: Separate logs do not address the inaccurate status.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 9: Evaluate project status