PMP Practice Questions: Engage Stakeholders

Identifying stakeholders and keeping them involved throughout the project.

14 questions · 10 key rules

Updated 17 November 2026 for the 2026 PMP exam content outline

Key facts

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Engage stakeholders1. A city is planning a predictive road construction project. The project manager has listed the sponsor and construction team. Which group should the project manager also identify as stakeholders?
    1. Only suppliers with signed contracts
    2. Residents and businesses affected by construction
    3. Only employees assigned to the project
    4. Competitors that are not affected by the project
    Show answer and explanation

    Answer: B. Residents and businesses affected by construction

    Residents and businesses affected by construction are stakeholders even if they do not work on the project. Identifying them early supports effective engagement. People, Task 4: Engage stakeholders.

    Why the others are wrong

    • Only suppliers with signed contracts: Stakeholders are not limited to contracted suppliers.
    • Only employees assigned to the project: Affected people outside the project team can also be stakeholders.
    • Competitors that are not affected by the project: Unaffected competitors have no stated stake in this project.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 4: Engage stakeholders

  2. Engage stakeholders2. A hybrid healthcare project is beginning its planning. The project manager knows the sponsor and clinical lead but is unsure which other groups will be affected by the new service. What should the project manager do next?
    1. Ask the sponsor and clinical lead to help identify affected groups
    2. Wait until affected groups contact the project team
    3. Limit the stakeholder list to the sponsor and clinical lead
    4. Ask the team to begin delivery before identifying other groups
    Show answer and explanation

    Answer: A. Ask the sponsor and clinical lead to help identify affected groups

    Consulting people who know the service can reveal stakeholders the project manager has not yet identified. This helps the project consider affected groups early. People, Task 4: Engage stakeholders.

    Why the others are wrong

    • Wait until affected groups contact the project team: Waiting for groups to come forward may leave important stakeholders unidentified.
    • Limit the stakeholder list to the sponsor and clinical lead: The sponsor and clinical lead may not represent every affected group.
    • Ask the team to begin delivery before identifying other groups: Starting delivery does not resolve the gap in stakeholder identification.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 4: Engage stakeholders

  3. Engage stakeholders3. During an agile product project, a pilot release reveals that a support team will need to handle new customer requests. The support team was not identified during initial planning. What should the project manager do next?
    1. Identify the support team as a stakeholder and discuss its involvement
    2. Keep the original stakeholder list unchanged until project closure
    3. Ask the product owner to resolve support requests without involving the support team
    4. Escalate the omission to the sponsor before contacting the support team
    Show answer and explanation

    Answer: A. Identify the support team as a stakeholder and discuss its involvement

    Stakeholder identification continues as the project reveals new affected groups. The project manager should recognize the support team and engage it about its role. People, Task 4: Engage stakeholders.

    Why the others are wrong

    • Keep the original stakeholder list unchanged until project closure: Leaving the list unchanged ignores a newly identified affected group.
    • Ask the product owner to resolve support requests without involving the support team: The product owner cannot substitute for involving the affected support team.
    • Escalate the omission to the sponsor before contacting the support team: Escalation is unnecessary before contacting the newly identified stakeholder.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 4: Engage stakeholders

  4. Engage stakeholders4. A project manager is starting a predictive construction project and has identified several community stakeholders. The manager needs to decide how closely to engage each one. What should the manager assess first?
    1. Each stakeholder’s interest in and influence on the project
    2. Each stakeholder’s preferred contract and payment terms
    3. The team’s preferred frequency for status meetings
    4. The sponsor’s preferred format for project reports
    Show answer and explanation

    Answer: A. Each stakeholder’s interest in and influence on the project

    Assessing stakeholders’ interest and influence helps the project manager determine appropriate engagement. This supports People, Task 4: Engage stakeholders.

    Why the others are wrong

    • Each stakeholder’s preferred contract and payment terms: Contract and payment terms do not establish the engagement needs of community stakeholders.
    • The team’s preferred frequency for status meetings: The team’s meeting preference does not reveal stakeholder interest or influence.
    • The sponsor’s preferred format for project reports: The sponsor’s report preference does not assess the other stakeholders.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 4: Engage stakeholders

Sign up free

Other PMP topics

GoConqr Original. Practice questions written with AI from the PMI 2026 PMP Examination Content Outline and settled project-management practice, each checked by a separate AI review. They are single- and multiple-response only: case sets, drag-and-drop, hotspot and pull-down items are not reproduced. Think a question is wrong? Use "Report" under it.

Independent study resource. Not affiliated with PMI. PMP and PMI are marks of the Project Management Institute.

© Visual Maths Resources Ltd

Feedback

What is it about?