PMP practice questions: Manage and control changes
Handling change requests, and submitting changes that need approval to the designated authority before implementation.
Updated 17 November 2026 for the 2026 PMP exam content outline
Key facts
Record proposed changes and follow the project's defined change control process.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 3: Manage and control changes
Assess each proposed change for its effects on scope, schedule, cost, quality, risk, benefits, and affected stakeholders.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 3: Manage and control changes
Submit changes requiring approval to the designated authority before implementation.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 3: Manage and control changes
In adaptive/agile work, prioritize backlog changes through the agreed process while applying formal control to changes that affect controlled commitments.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 3: Manage and control changes
Record each change decision and its rationale, including rejected and deferred requests.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 3: Manage and control changes
Communicate the status and decisions on proposed changes to affected stakeholders promptly.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 3: Manage and control changes
Plan approved changes with the responsible team, including necessary resources, timing, and dependencies.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 3: Manage and control changes
Implement approved changes and monitor their effects against the intended outcomes.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 3: Manage and control changes
Update affected plans, baselines, requirements, and other project artifacts to reflect approved changes.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 3: Manage and control changes
Communicate updated documents and implementation responsibilities to those who need them.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 3: Manage and control changes
Sample questions
1. During a predictive construction project, a client requests an additional entrance after the scope baseline is approved. What should the project manager do next?
- Ask the team to build the entrance immediately.
- Reject the request because the baseline is approved.
- Ask the sponsor to approve the design without review.
- Submit the request through the agreed change control process.
Answer: D. Submit the request through the agreed change control process.
The agreed change control process provides a way to assess and decide on a proposed change. An approved baseline does not prevent changes, but changes should be controlled.
- Ask the team to build the entrance immediately: Starting work bypasses change assessment and approval.
- Reject the request because the baseline is approved: An approved baseline can still be changed through the agreed process.
- Ask the sponsor to approve the design without review: Sponsor approval alone may bypass the agreed review process.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 3: Manage and control changes
2. A change control board is considering a new reporting requirement for a predictive healthcare project. The project manager has received the request but has not assessed it. What should the project manager do next?
- Update the schedule baseline to include the new work.
- Direct the team to start the report design.
- Assess the change's effects on scope, schedule, and cost.
- Ask the board to approve the request before analysis.
Answer: C. Assess the change's effects on scope, schedule, and cost.
Assessing impacts gives the change control board information to make a decision. Baselines and work should not be changed before the required approval.
- Update the schedule baseline to include the new work: Updating the baseline before approval bypasses change control.
- Direct the team to start the report design: Starting design work before approval commits project resources prematurely.
- Ask the board to approve the request before analysis: An uninformed decision may overlook important impacts.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 3: Manage and control changes
3. A hybrid software project uses a prioritized backlog, but changes to its regulatory commitments require formal approval. A stakeholder requests a backlog change that could affect a regulatory commitment. What should the project manager do next?
- Assess the impact and use the agreed approval process if required.
- Let the team implement the item in the next iteration.
- Defer the request until all development work is complete.
- Ask the stakeholder to revise the commitment directly.
Answer: A. Assess the impact and use the agreed approval process if required.
The project manager should assess whether the request affects the regulatory commitment and apply the agreed approval process when required. A backlog change can still be subject to formal controls.
- Let the team implement the item in the next iteration: Implementing the item first could bypass a required approval.
- Defer the request until all development work is complete: Automatic deferral avoids assessing the request's impact and priority.
- Ask the stakeholder to revise the commitment directly: A stakeholder should not independently revise a controlled commitment.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 3: Manage and control changes
4. On a predictive construction project, the change control board has not yet decided on a proposed design change. A stakeholder asks whether it can be included in the next delivery. What should the project manager communicate?
- The change is approved for the next delivery.
- The change is pending a decision.
- The change is rejected until implementation starts.
- The change is included in the current baseline.
Answer: B. The change is pending a decision.
The project manager should communicate the proposal’s current status without implying that it has been approved. This supports Business Environment, Task 3: Manage and control changes.
- The change is approved for the next delivery: A pending proposal has not been approved.
- The change is rejected until implementation starts: A pending decision does not mean the proposal was rejected.
- The change is included in the current baseline: A proposed change is not automatically part of the baseline.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 3: Manage and control changes