PMP practice questions: Manage and control changes

Handling change requests, and submitting changes that need approval to the designated authority before implementation.

11 questions · 10 key rules

Updated 17 November 2026 for the 2026 PMP exam content outline

Key facts

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Change control1. During a predictive construction project, a client requests an additional entrance after the scope baseline is approved. What should the project manager do next?
    1. Ask the team to build the entrance immediately.
    2. Reject the request because the baseline is approved.
    3. Ask the sponsor to approve the design without review.
    4. Submit the request through the agreed change control process.
    Show answer and explanation

    Answer: D. Submit the request through the agreed change control process.

    The agreed change control process provides a way to assess and decide on a proposed change. An approved baseline does not prevent changes, but changes should be controlled.

    Why the others are wrong

    • Ask the team to build the entrance immediately: Starting work bypasses change assessment and approval.
    • Reject the request because the baseline is approved: An approved baseline can still be changed through the agreed process.
    • Ask the sponsor to approve the design without review: Sponsor approval alone may bypass the agreed review process.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 3: Manage and control changes

  2. Change control2. A change control board is considering a new reporting requirement for a predictive healthcare project. The project manager has received the request but has not assessed it. What should the project manager do next?
    1. Update the schedule baseline to include the new work.
    2. Direct the team to start the report design.
    3. Assess the change's effects on scope, schedule, and cost.
    4. Ask the board to approve the request before analysis.
    Show answer and explanation

    Answer: C. Assess the change's effects on scope, schedule, and cost.

    Assessing impacts gives the change control board information to make a decision. Baselines and work should not be changed before the required approval.

    Why the others are wrong

    • Update the schedule baseline to include the new work: Updating the baseline before approval bypasses change control.
    • Direct the team to start the report design: Starting design work before approval commits project resources prematurely.
    • Ask the board to approve the request before analysis: An uninformed decision may overlook important impacts.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 3: Manage and control changes

  3. Change control3. A hybrid software project uses a prioritized backlog, but changes to its regulatory commitments require formal approval. A stakeholder requests a backlog change that could affect a regulatory commitment. What should the project manager do next?
    1. Assess the impact and use the agreed approval process if required.
    2. Let the team implement the item in the next iteration.
    3. Defer the request until all development work is complete.
    4. Ask the stakeholder to revise the commitment directly.
    Show answer and explanation

    Answer: A. Assess the impact and use the agreed approval process if required.

    The project manager should assess whether the request affects the regulatory commitment and apply the agreed approval process when required. A backlog change can still be subject to formal controls.

    Why the others are wrong

    • Let the team implement the item in the next iteration: Implementing the item first could bypass a required approval.
    • Defer the request until all development work is complete: Automatic deferral avoids assessing the request's impact and priority.
    • Ask the stakeholder to revise the commitment directly: A stakeholder should not independently revise a controlled commitment.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 3: Manage and control changes

  4. Change control4. On a predictive construction project, the change control board has not yet decided on a proposed design change. A stakeholder asks whether it can be included in the next delivery. What should the project manager communicate?
    1. The change is approved for the next delivery.
    2. The change is pending a decision.
    3. The change is rejected until implementation starts.
    4. The change is included in the current baseline.
    Show answer and explanation

    Answer: B. The change is pending a decision.

    The project manager should communicate the proposal’s current status without implying that it has been approved. This supports Business Environment, Task 3: Manage and control changes.

    Why the others are wrong

    • The change is approved for the next delivery: A pending proposal has not been approved.
    • The change is rejected until implementation starts: A pending decision does not mean the proposal was rejected.
    • The change is included in the current baseline: A proposed change is not automatically part of the baseline.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 3: Manage and control changes

Sign up free

Other PMP topics

GoConqr Original. Practice questions written with AI from the PMI 2026 PMP Examination Content Outline and settled project-management practice, each checked by a separate AI review. They are single- and multiple-response only: case sets, drag-and-drop, hotspot and pull-down items are not reproduced. Think a question is wrong? Use "Report" under it.