Exams · US

PMP Practice Questions: Plan and Manage Schedule

Building the schedule and keeping work on track against it.

14 questions · 10 key rules

Updated 17 November 2026 for the 2026 PMP exam content outline

Key facts

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Schedule1. A software team uses an adaptive approach to develop a product. Requirements are expected to change as users review increments. How should the project manager prepare the schedule?
    1. Fix all task dates before collecting user feedback.
    2. Set a complete schedule baseline and prohibit changes during development.
    3. Defer all scheduling until the product requirements are stable.
    4. Plan near-term work in detail and revise later plans as learning occurs.
    Show answer and explanation

    Answer: D. Plan near-term work in detail and revise later plans as learning occurs.

    An adaptive schedule can detail near-term work while allowing later plans to evolve as the team learns. This supports feedback without abandoning scheduling. Process, Task 8: Plan and manage schedule.

    Why the others are wrong

    • Fix all task dates before collecting user feedback: Fixed dates for all tasks limit the ability to respond to learning.
    • Set a complete schedule baseline and prohibit changes during development: Prohibiting changes conflicts with the expected evolution of requirements.
    • Defer all scheduling until the product requirements are stable: Waiting for stable requirements would leave the team without a useful schedule.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 8: Plan and manage schedule

  2. Schedule2. A hybrid project combines predictive facility work with adaptive software delivery. Equipment installation must finish before software can be tested on site. What should the project manager do when preparing the schedule?
    1. Schedule software testing independently of the installation dates.
    2. Include the installation dependency and coordinate it with software delivery plans.
    3. Fix every software task date to match the construction baseline.
    4. Delay the facility schedule until all software requirements are final.
    Show answer and explanation

    Answer: B. Include the installation dependency and coordinate it with software delivery plans.

    The schedule should reflect the dependency between installation and on-site testing while accommodating the different approaches. Coordination helps both teams plan around the shared milestone. Process, Task 8: Plan and manage schedule.

    Why the others are wrong

    • Schedule software testing independently of the installation dates: Independent dates could place testing before the equipment is available.
    • Fix every software task date to match the construction baseline: Fixing every software task date unnecessarily restricts adaptive planning.
    • Delay the facility schedule until all software requirements are final: Finalizing all software requirements is not necessary to plan facility work.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 8: Plan and manage schedule

  3. Schedule3. A predictive project needs a planned system outage for installation. Operations has scheduled a major reporting cycle for the same day. What should the project manager do next?
    1. Proceed with installation and notify operations afterward.
    2. Ask the sponsor to cancel the reporting cycle.
    3. Meet with operations to agree on a suitable outage window.
    4. Move the installation date without consulting operations.
    Show answer and explanation

    Answer: C. Meet with operations to agree on a suitable outage window.

    Coordinating with operations helps the project manager find an outage window that supports both the project and business needs. This applies Process, Task 8: Plan and manage schedule.

    Why the others are wrong

    • Proceed with installation and notify operations afterward: Proceeding without agreement could disrupt the reporting cycle.
    • Ask the sponsor to cancel the reporting cycle: Escalating before discussing alternatives is premature.
    • Move the installation date without consulting operations: Moving the date without consultation may create another conflict.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 8: Plan and manage schedule

  4. Schedule4. In a hybrid project, a release depends on an interface from another project. That project's manager reports a likely delay, but its impact is not yet known. What should the project manager do next?
    1. Assess the dependency and schedule impact with the other project manager.
    2. Rebaseline the release date using the reported delay.
    3. Escalate the delay to both sponsors for a decision.
    4. Remove the interface work from the release backlog.
    Show answer and explanation

    Answer: A. Assess the dependency and schedule impact with the other project manager.

    Assessing the dependency together establishes the likely effect on the release and supports a coordinated response. This applies Process, Task 8: Plan and manage schedule.

    Why the others are wrong

    • Rebaseline the release date using the reported delay: Rebaselining before assessing the impact is premature.
    • Escalate the delay to both sponsors for a decision: Escalation may be unnecessary before the impact is understood.
    • Remove the interface work from the release backlog: Removing the work without assessing the impact may compromise the release.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 8: Plan and manage schedule

Sign up free

Other PMP topics

GoConqr Original. Practice questions written with AI from the PMI 2026 PMP Examination Content Outline and settled project-management practice, each checked by a separate AI review. They are single- and multiple-response only: case sets, drag-and-drop, hotspot and pull-down items are not reproduced. Think a question is wrong? Use "Report" under it.

Independent study resource. Not affiliated with PMI. PMP and PMI are marks of the Project Management Institute.

© Visual Maths Resources Ltd

Feedback

What is it about?