PMP practice questions: Lead the project team

Guiding, supporting and motivating the team to deliver the work.

13 questions · 10 key rules

Updated 17 November 2026 for the 2026 PMP exam content outline

Key facts

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Lead the team1. During a software project, team members repeatedly miss a previously agreed handoff time because their working hours have changed. What should the project manager do next?
    1. Escalate each missed handoff to the sponsor.
    2. Reassign the handoffs to members with longer working hours.
    3. Keep the existing agreement until the project ends.
    4. Discuss the constraint with the team and agree on revised expectations.
    Show answer and explanation

    Answer: D. Discuss the constraint with the team and agree on revised expectations.

    The project manager should work with the team to review expectations that no longer fit its circumstances. A revised agreement makes future handoffs clearer and supports People, Task 3: Lead the project team.

    Why the others are wrong

    • Escalate each missed handoff to the sponsor: Escalation is premature when the team can address the constraint.
    • Reassign the handoffs to members with longer working hours: Reassignment without discussion may not resolve the underlying constraint.
    • Keep the existing agreement until the project ends: Keeping an impractical agreement does not address repeated missed handoffs.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 3: Lead the project team

  2. Lead the team2. An adaptive software team frequently waits for the project manager to assign each technical task. The team has the skills to organize its own work. What should the project manager do next?
    1. Ask the sponsor to assign tasks at each planning meeting.
    2. Let team members coordinate task assignments within agreed boundaries.
    3. Assign tasks individually to keep workloads consistent.
    4. Require the product owner to approve every task assignment.
    Show answer and explanation

    Answer: B. Let team members coordinate task assignments within agreed boundaries.

    Empowering the team means giving capable members authority to organize their work within agreed boundaries. This supports ownership while retaining appropriate project oversight. People, Task 3: Lead the project team.

    Why the others are wrong

    • Ask the sponsor to assign tasks at each planning meeting: The sponsor need not manage the team's task assignments.
    • Assign tasks individually to keep workloads consistent: Individual assignments preserve unnecessary dependence on the project manager.
    • Require the product owner to approve every task assignment: Approval of every task assignment limits the team's autonomy.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 3: Lead the project team

  3. Lead the team3. On a hybrid healthcare project, team members want to resolve a recurring handoff problem themselves. The proposed changes may affect another department's work. What should the project manager do next?
    1. Direct the team to implement its preferred solution immediately.
    2. Escalate the problem to the sponsor for a final decision.
    3. Ask the team to stop work until management assigns a solution.
    4. Help the team assess the impact and involve the affected department.
    Show answer and explanation

    Answer: D. Help the team assess the impact and involve the affected department.

    The project manager can empower the team to develop a solution while helping it consider impacts beyond its authority. Involving the affected department supports a workable agreement before changes are made. People, Task 3: Lead the project team.

    Why the others are wrong

    • Direct the team to implement its preferred solution immediately: Immediate implementation skips assessment of the impact on another department.
    • Escalate the problem to the sponsor for a final decision: Escalation is premature when the team can assess and discuss the issue.
    • Ask the team to stop work until management assigns a solution: Stopping work and awaiting an assigned solution removes the team's initiative.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 3: Lead the project team

  4. Lead the team4. On a predictive construction project, installation errors have increased. The team disagrees about the cause. What should the project manager do first?
    1. Replace the installation lead immediately
    2. Ask the sponsor to select a solution
    3. Add inspections without investigating the errors
    4. Examine the errors with the team to identify their cause
    Show answer and explanation

    Answer: D. Examine the errors with the team to identify their cause

    The project manager should work with the team to understand the cause before choosing a solution. This supports People, Task 3: Lead the project team.

    Why the others are wrong

    • Replace the installation lead immediately: Replacing the lead assumes the cause without evidence.
    • Ask the sponsor to select a solution: The sponsor lacks the team's direct knowledge of the errors.
    • Add inspections without investigating the errors: More inspections may detect errors without addressing their cause.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 3: Lead the project team

Sign up free

Other PMP topics

GoConqr Original. Practice questions written with AI from the PMI 2026 PMP Examination Content Outline and settled project-management practice, each checked by a separate AI review. They are single- and multiple-response only: case sets, drag-and-drop, hotspot and pull-down items are not reproduced. Think a question is wrong? Use "Report" under it.

Independent study resource. Not affiliated with PMI. PMP and PMI are marks of the Project Management Institute.