Exams · US

PMP Practice Questions: Manage Conflicts

Spotting the source of a conflict and resolving it so work can continue.

14 questions · 10 key rules

Updated 17 November 2026 for the 2026 PMP exam content outline

Key facts

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Conflicts1. On a predictive construction project, two team leads argue because each needs the same specialist during the same week. What conflict source should the project manager investigate first?
    1. Different quality standards
    2. Competing resource needs
    3. Unclear acceptance criteria
    4. A missing communication channel
    Show answer and explanation

    Answer: B. Competing resource needs

    The leads need the same limited resource at the same time, suggesting a resource conflict. People, Task 2: Manage conflicts includes identifying the source before choosing a resolution.

    Why the others are wrong

    • Different quality standards: Different quality standards are not indicated by the dispute.
    • Unclear acceptance criteria: Acceptance criteria are not the issue described.
    • A missing communication channel: The leads are communicating, even though they disagree.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 2: Manage conflicts

  2. Conflicts2. On an agile product team, a developer and a tester repeatedly disagree over who should update automated tests. Their responsibilities were never discussed. What should the project manager do next to identify the conflict source?
    1. Ask the sponsor to assign the testing work
    2. Discuss each person's understanding of the responsibilities
    3. Compare the team's quality results with its targets
    4. Add the disputed work to the next iteration
    Show answer and explanation

    Answer: B. Discuss each person's understanding of the responsibilities

    Discussing each person's understanding can reveal whether unclear responsibilities are causing the conflict. People, Task 2: Manage conflicts calls for identifying the source before implementing a resolution.

    Why the others are wrong

    • Ask the sponsor to assign the testing work: A sponsor assignment skips investigation of the disagreement.
    • Compare the team's quality results with its targets: Quality targets do not establish why responsibilities are disputed.
    • Add the disputed work to the next iteration: Scheduling the work does not clarify who is responsible.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 2: Manage conflicts

  3. Conflicts3. In a hybrid healthcare project, operations wants an early release while clinicians want more time for safety checks. Meetings have become tense, and each group blames the other. What should the project manager do first to identify the conflict source?
    1. Ask the sponsor to choose a release date
    2. Direct the team to complete the safety checks first
    3. Meet with both groups to understand their priorities
    4. Move the release decision to the change control board
    Show answer and explanation

    Answer: C. Meet with both groups to understand their priorities

    Understanding both groups' priorities helps reveal whether the conflict comes from competing objectives. People, Task 2: Manage conflicts requires identifying the source rather than relying on blame.

    Why the others are wrong

    • Ask the sponsor to choose a release date: A sponsor decision may be needed later, but it skips investigation.
    • Direct the team to complete the safety checks first: Directing the work assumes a resolution before examining the conflict.
    • Move the release decision to the change control board: Escalating the decision does not first identify the source.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 2: Manage conflicts

  4. Conflicts4. During a software sprint, two developers disagree about how to implement a feature. Their discussion is delaying work. What should the project manager do first?
    1. Assign the feature to a different developer immediately.
    2. Ask each developer to explain their concerns and constraints.
    3. Ask the sponsor to choose the technical solution.
    4. Tell both developers to follow the senior developer's preference.
    Show answer and explanation

    Answer: B. Ask each developer to explain their concerns and constraints.

    Understanding each person's concerns and constraints helps the project manager assess the conflict before choosing a response. This supports People, Task 2: Manage conflicts.

    Why the others are wrong

    • Assign the feature to a different developer immediately: Reassigning the work avoids understanding the disagreement.
    • Ask the sponsor to choose the technical solution: Escalating before assessing the conflict is premature.
    • Tell both developers to follow the senior developer's preference: Seniority alone does not establish the best resolution.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 2: Manage conflicts

Sign up free

Other PMP topics

GoConqr Original. Practice questions written with AI from the PMI 2026 PMP Examination Content Outline and settled project-management practice, each checked by a separate AI review. They are single- and multiple-response only: case sets, drag-and-drop, hotspot and pull-down items are not reproduced. Think a question is wrong? Use "Report" under it.

Independent study resource. Not affiliated with PMI. PMP and PMI are marks of the Project Management Institute.

© Visual Maths Resources Ltd

Feedback

What is it about?