Exams · US
PMP Practice Questions: Manage Conflicts
Spotting the source of a conflict and resolving it so work can continue.
Updated 17 November 2026 for the 2026 PMP exam content outline
Key facts
Identify conflict sources such as competing priorities, scarce resources, unclear responsibilities, technical differences, and communication breakdowns.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 2: Manage conflicts
Listen to the parties separately or together to distinguish the underlying issue from its symptoms.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 2: Manage conflicts
Analyze the conflict's context, including urgency, impact, relationships, cultural differences, and the parties' interests and authority.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 2: Manage conflicts
Choose a resolution strategy suited to the situation, seeking collaborative problem-solving when the parties can address the underlying issue together.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 2: Manage conflicts
Agree on resolution actions, owners, and timing with the affected parties, then follow up to confirm that the conflict is resolved.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 2: Manage conflicts
Escalate a conflict when it exceeds the project manager's authority or cannot be resolved at the appropriate working level.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 2: Manage conflicts
Communicate conflict management principles to the team and relevant external stakeholders, including respectful discussion and appropriate escalation.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 2: Manage conflicts
Establish common ground rules with the team and make expectations for conduct and decision-making visible and accessible.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 2: Manage conflicts
Model and reinforce ground rules so team members can raise concerns without fear of retaliation.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 2: Manage conflicts
Address ground rule violations promptly and fairly, agree on corrective action, and follow up on adherence.
PMI, Project Management Professional Examination Content Outline - 2026, Domain I People, Task 2: Manage conflicts
Sample questions
1. On a predictive construction project, two team leads argue because each needs the same specialist during the same week. What conflict source should the project manager investigate first?
- Different quality standards
- Competing resource needs
- Unclear acceptance criteria
- A missing communication channel
Answer: B. Competing resource needs
The leads need the same limited resource at the same time, suggesting a resource conflict. People, Task 2: Manage conflicts includes identifying the source before choosing a resolution.
- Different quality standards: Different quality standards are not indicated by the dispute.
- Unclear acceptance criteria: Acceptance criteria are not the issue described.
- A missing communication channel: The leads are communicating, even though they disagree.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 2: Manage conflicts
2. On an agile product team, a developer and a tester repeatedly disagree over who should update automated tests. Their responsibilities were never discussed. What should the project manager do next to identify the conflict source?
- Ask the sponsor to assign the testing work
- Discuss each person's understanding of the responsibilities
- Compare the team's quality results with its targets
- Add the disputed work to the next iteration
Answer: B. Discuss each person's understanding of the responsibilities
Discussing each person's understanding can reveal whether unclear responsibilities are causing the conflict. People, Task 2: Manage conflicts calls for identifying the source before implementing a resolution.
- Ask the sponsor to assign the testing work: A sponsor assignment skips investigation of the disagreement.
- Compare the team's quality results with its targets: Quality targets do not establish why responsibilities are disputed.
- Add the disputed work to the next iteration: Scheduling the work does not clarify who is responsible.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 2: Manage conflicts
3. In a hybrid healthcare project, operations wants an early release while clinicians want more time for safety checks. Meetings have become tense, and each group blames the other. What should the project manager do first to identify the conflict source?
- Ask the sponsor to choose a release date
- Direct the team to complete the safety checks first
- Meet with both groups to understand their priorities
- Move the release decision to the change control board
Answer: C. Meet with both groups to understand their priorities
Understanding both groups' priorities helps reveal whether the conflict comes from competing objectives. People, Task 2: Manage conflicts requires identifying the source rather than relying on blame.
- Ask the sponsor to choose a release date: A sponsor decision may be needed later, but it skips investigation.
- Direct the team to complete the safety checks first: Directing the work assumes a resolution before examining the conflict.
- Move the release decision to the change control board: Escalating the decision does not first identify the source.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 2: Manage conflicts
4. During a software sprint, two developers disagree about how to implement a feature. Their discussion is delaying work. What should the project manager do first?
- Assign the feature to a different developer immediately.
- Ask each developer to explain their concerns and constraints.
- Ask the sponsor to choose the technical solution.
- Tell both developers to follow the senior developer's preference.
Answer: B. Ask each developer to explain their concerns and constraints.
Understanding each person's concerns and constraints helps the project manager assess the conflict before choosing a response. This supports People, Task 2: Manage conflicts.
- Assign the feature to a different developer immediately: Reassigning the work avoids understanding the disagreement.
- Ask the sponsor to choose the technical solution: Escalating before assessing the conflict is premature.
- Tell both developers to follow the senior developer's preference: Seniority alone does not establish the best resolution.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 2: Manage conflicts