  1. Impediments and issues1. A predictive construction project has a blocked inspection. The next activity cannot start until the inspection is complete, and the delay will use all remaining schedule float. What should the project manager evaluate next?
    1. The cost of replacing the inspection provider immediately
    2. The team's preference for a new reporting format
    3. The sponsor's availability for the next status meeting
    4. The effect of further delay on the completion date
    Show answer and explanation

    Answer: D. The effect of further delay on the completion date

    Further delay could affect the project completion date because the remaining float has been used. Evaluating that impact helps the project manager decide how urgently to address the impediment. This applies Business Environment, Task 4: Remove impediments and manage issues.

    Why the others are wrong

    • The cost of replacing the inspection provider immediately: Replacing the provider is a possible intervention, but its cost alone does not establish the schedule impact.
    • The team's preference for a new reporting format: A reporting format does not measure the effect of the blocked inspection.
    • The sponsor's availability for the next status meeting: The sponsor's availability does not establish the impact of the delay.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 4: Remove impediments and manage issues

  2. Impediments and issues2. An agile team planned to complete 40 units of work this sprint. A blocked test environment prevents completion of 12 units, while the remaining work is unaffected. What proportion of the planned work is affected?
    1. 12%
    2. 20%
    3. 30%
    4. 40%
    Show answer and explanation

    Answer: C. 30%

    Divide the 12 affected units by the 40 planned units: 12 ÷ 40 = 0.30, or 30%. This quantifies the impediment's impact on planned sprint work under Business Environment, Task 4: Remove impediments and manage issues.

    Why the others are wrong

    • 12%: 12% treats the number of affected units as a percentage.
    • 20%: 20% understates the share affected by the blocked environment.
    • 40%: 40% uses the total planned units as the percentage affected.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 4: Remove impediments and manage issues

  3. Impediments and issues3. During a sprint, a missing access approval blocks five developers from testing a feature. A separate formatting question affects one draft report but does not stop work. Which impediment should the project manager prioritize?
    1. The formatting question, because the report is visible to stakeholders
    2. The access approval, because it blocks more people from working
    3. Both equally, because each was raised during the sprint
    4. The formatting question, because it may be quicker to resolve
    Show answer and explanation

    Answer: B. The access approval, because it blocks more people from working

    The access approval is the higher priority because it is stopping work for more team members. Addressing it first can restore the team's ability to test the feature. Business Environment, Task 4: Remove impediments and manage issues.

    Why the others are wrong

    • The formatting question, because the report is visible to stakeholders: Visibility alone does not outweigh the work stoppage.
    • Both equally, because each was raised during the sprint: Being raised during the same sprint does not make their impacts equal.
    • The formatting question, because it may be quicker to resolve: Speed of resolution alone does not determine priority.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 4: Remove impediments and manage issues

  4. Impediments and issues4. On a predictive healthcare project, a permit delay threatens the construction schedule. The project manager cannot approve the permit, and the agreed escalation contact is the facilities director. What should the project manager do next?
    1. Revise the schedule baseline to include the expected delay
    2. Ask the construction team to proceed without the permit
    3. Wait until the permit delay affects the project completion date
    4. Highlight the impact and seek the facilities director's help
    Show answer and explanation

    Answer: D. Highlight the impact and seek the facilities director's help

    The project manager should highlight the threatened schedule impact to the agreed contact who can help address the impediment. Early escalation supports action before the delay causes further disruption. Business Environment, Task 4: Remove impediments and manage issues.

    Why the others are wrong

    • Revise the schedule baseline to include the expected delay: A threatened delay alone does not authorize a baseline revision.
    • Ask the construction team to proceed without the permit: Proceeding without the permit could create further problems.
    • Wait until the permit delay affects the project completion date: Waiting can allow the impediment's impact to grow.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 4: Remove impediments and manage issues

Sign up free

Other PMP topics

GoConqr Original. Practice questions written with AI from the PMI 2026 PMP Examination Content Outline and settled project-management practice, each checked by a separate AI review. They are single- and multiple-response only: case sets, drag-and-drop, hotspot and pull-down items are not reproduced. Think a question is wrong? Use "Report" under it.

Independent study resource. Not affiliated with PMI. PMP and PMI are marks of the Project Management Institute.

© Visual Maths Resources Ltd

Feedback

What is it about?