Exams · US
PMP practice questions: Remove impediments and manage issues
Clearing blockers and dealing with issues that get in the team's way.
Updated 17 November 2026 for the 2026 PMP exam content outline
Key facts
Evaluate an impediment’s effect on delivery, cost, schedule, quality, and affected stakeholders.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 4: Remove impediments and manage issues
Prioritize impediments by impact, urgency, and the work or dependencies they block.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 4: Remove impediments and manage issues
Make impediments visible to the team and relevant stakeholders so they can coordinate a response.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 4: Remove impediments and manage issues
Identify the cause of an impediment before selecting an intervention to remove or minimize it.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 4: Remove impediments and manage issues
Assign an owner and agree on actions and a target date for addressing each significant impediment.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 4: Remove impediments and manage issues
Escalate an impediment when its resolution exceeds the team’s authority or requires a decision from others.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 4: Remove impediments and manage issues
Reassess impediments regularly and verify that interventions have restored progress or reduced their impact.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 4: Remove impediments and manage issues
A risk is an uncertain future event or condition, whereas an issue is a current problem requiring attention.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 4: Remove impediments and manage issues
When a risk occurs and creates a problem, manage the resulting issue and update the relevant records.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 4: Remove impediments and manage issues
Collaborate with affected stakeholders to agree on an issue resolution, its owner, and follow-up actions.
PMI, Project Management Professional Examination Content Outline - 2026, Domain III Business Environment, Task 4: Remove impediments and manage issues
Sample questions
1. A predictive construction project has a blocked inspection. The next activity cannot start until the inspection is complete, and the delay will use all remaining schedule float. What should the project manager evaluate next?
- The cost of replacing the inspection provider immediately
- The team's preference for a new reporting format
- The sponsor's availability for the next status meeting
- The effect of further delay on the completion date
Answer: D. The effect of further delay on the completion date
Further delay could affect the project completion date because the remaining float has been used. Evaluating that impact helps the project manager decide how urgently to address the impediment. This applies Business Environment, Task 4: Remove impediments and manage issues.
- The cost of replacing the inspection provider immediately: Replacing the provider is a possible intervention, but its cost alone does not establish the schedule impact.
- The team's preference for a new reporting format: A reporting format does not measure the effect of the blocked inspection.
- The sponsor's availability for the next status meeting: The sponsor's availability does not establish the impact of the delay.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 4: Remove impediments and manage issues
2. An agile team planned to complete 40 units of work this sprint. A blocked test environment prevents completion of 12 units, while the remaining work is unaffected. What proportion of the planned work is affected?
- 12%
- 20%
- 30%
- 40%
Answer: C. 30%
Divide the 12 affected units by the 40 planned units: 12 ÷ 40 = 0.30, or 30%. This quantifies the impediment's impact on planned sprint work under Business Environment, Task 4: Remove impediments and manage issues.
- 12%: 12% treats the number of affected units as a percentage.
- 20%: 20% understates the share affected by the blocked environment.
- 40%: 40% uses the total planned units as the percentage affected.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 4: Remove impediments and manage issues
3. During a sprint, a missing access approval blocks five developers from testing a feature. A separate formatting question affects one draft report but does not stop work. Which impediment should the project manager prioritize?
- The formatting question, because the report is visible to stakeholders
- The access approval, because it blocks more people from working
- Both equally, because each was raised during the sprint
- The formatting question, because it may be quicker to resolve
Answer: B. The access approval, because it blocks more people from working
The access approval is the higher priority because it is stopping work for more team members. Addressing it first can restore the team's ability to test the feature. Business Environment, Task 4: Remove impediments and manage issues.
- The formatting question, because the report is visible to stakeholders: Visibility alone does not outweigh the work stoppage.
- Both equally, because each was raised during the sprint: Being raised during the same sprint does not make their impacts equal.
- The formatting question, because it may be quicker to resolve: Speed of resolution alone does not determine priority.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 4: Remove impediments and manage issues
4. On a predictive healthcare project, a permit delay threatens the construction schedule. The project manager cannot approve the permit, and the agreed escalation contact is the facilities director. What should the project manager do next?
- Revise the schedule baseline to include the expected delay
- Ask the construction team to proceed without the permit
- Wait until the permit delay affects the project completion date
- Highlight the impact and seek the facilities director's help
Answer: D. Highlight the impact and seek the facilities director's help
The project manager should highlight the threatened schedule impact to the agreed contact who can help address the impediment. Early escalation supports action before the delay causes further disruption. Business Environment, Task 4: Remove impediments and manage issues.
- Revise the schedule baseline to include the expected delay: A threatened delay alone does not authorize a baseline revision.
- Ask the construction team to proceed without the permit: Proceeding without the permit could create further problems.
- Wait until the permit delay affects the project completion date: Waiting can allow the impediment's impact to grow.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain III Business Environment, Task 4: Remove impediments and manage issues