PMP practice questions: Manage stakeholder expectations

Keeping expectations realistic and handling them as the project moves on.

14 questions · 10 key rules

Updated 17 November 2026 for the 2026 PMP exam content outline

Key facts

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Manage expectations1. A project manager is starting a predictive project to replace a hospital scheduling system. Both hospital staff and patients will use it. What should the project manager do first to identify their expectations?
    1. Ask representatives of both groups what they need from the system.
    2. Ask the technical team to define the users’ needs.
    3. Use the sponsor’s expectations for both customer groups.
    4. Wait until the system is built to gather user feedback.
    Show answer and explanation

    Answer: A. Ask representatives of both groups what they need from the system.

    Speaking with representatives of both groups helps identify their potentially different expectations. This supports People, Task 6: Manage stakeholder expectations.

    Why the others are wrong

    • Ask the technical team to define the users’ needs: The technical team may not know what both customer groups expect.
    • Use the sponsor’s expectations for both customer groups: The sponsor may not represent all staff and patient expectations.
    • Wait until the system is built to gather user feedback: Waiting until delivery delays the identification of expectations.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 6: Manage stakeholder expectations

  2. Manage expectations2. A hybrid product team learns that an external customer wants faster delivery, while an internal support team expects more time for training. What should the project manager do next?
    1. Promise the customer an earlier release date.
    2. Discuss the expectations with both groups to understand their priorities.
    3. Ask the support team to reduce its training needs.
    4. Escalate the disagreement to the sponsor for an immediate decision.
    Show answer and explanation

    Answer: B. Discuss the expectations with both groups to understand their priorities.

    Discussing the expectations with both groups helps the project manager understand their priorities before proposing a response. This supports People, Task 6: Manage stakeholder expectations.

    Why the others are wrong

    • Promise the customer an earlier release date: A delivery promise is premature before the expectations are understood.
    • Ask the support team to reduce its training needs: Reducing training needs without discussion dismisses an internal expectation.
    • Escalate the disagreement to the sponsor for an immediate decision: Immediate escalation skips the project manager’s initial assessment.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 6: Manage stakeholder expectations

  3. Manage expectations3. An adaptive team is beginning work on a public service application. Internal service staff and external applicants have different roles in the process. Which two actions should the project manager take to identify their expectations? Choose two.
    1. Interview service staff about their needs and concerns.
    2. Ask applicants what outcomes they expect from the application.
    3. Treat the project sponsor’s priorities as the expectations of all users.
    4. Ask developers to decide which user expectations matter.
    5. Record only expectations that can be delivered in the first iteration.
    Show answer and explanation

    Answer: A. Interview service staff about their needs and concerns., B. Ask applicants what outcomes they expect from the application.

    Gathering input from both customer groups helps reveal expectations related to their different roles. This supports People, Task 6: Manage stakeholder expectations.

    Why the others are wrong

    • Treat the project sponsor’s priorities as the expectations of all users: The sponsor’s priorities may not represent either user group fully.
    • Ask developers to decide which user expectations matter: Developers cannot reliably determine user expectations without user input.
    • Record only expectations that can be delivered in the first iteration: Limiting identification to the first iteration may miss important expectations.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 6: Manage stakeholder expectations

  4. Manage expectations4. During planning for a predictive construction project, the external customer requests a “high-quality finish.” The internal operations team will maintain the facility. What should the project manager do to identify the expectations behind this request?
    1. Meet with the customer and operations team to clarify the finish expected.
    2. Add the phrase to the scope baseline without further detail.
    3. Ask the contractor to select the finish it normally uses.
    4. Ask the sponsor to approve a finish before consulting users.
    Show answer and explanation

    Answer: A. Meet with the customer and operations team to clarify the finish expected.

    The phrase is open to interpretation, so discussion with both groups can reveal the expectations behind it. This supports People, Task 6: Manage stakeholder expectations.

    Why the others are wrong

    • Add the phrase to the scope baseline without further detail: An unclear phrase does not establish a shared expectation.
    • Ask the contractor to select the finish it normally uses: The contractor’s usual choice may not meet customer or operations needs.
    • Ask the sponsor to approve a finish before consulting users: Approval before consultation may overlook relevant expectations.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain I People, Task 6: Manage stakeholder expectations

Sign up free

Other PMP topics

GoConqr Original. Practice questions written with AI from the PMI 2026 PMP Examination Content Outline and settled project-management practice, each checked by a separate AI review. They are single- and multiple-response only: case sets, drag-and-drop, hotspot and pull-down items are not reproduced. Think a question is wrong? Use "Report" under it.

Independent study resource. Not affiliated with PMI. PMP and PMI are marks of the Project Management Institute.

© Visual Maths Resources Ltd

Feedback

What is it about?