PMP practice questions: Integrated plan and delivery

Bringing the plan's parts together and choosing how the project will deliver.

13 questions · 11 key rules

Updated 17 November 2026 for the 2026 PMP exam content outline

Key facts

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Integrated plan1. A public agency is starting a project for 12 service offices. Leaders disagree about which services the project must support. What should the project manager do next?
    1. Estimate the schedule using a similar project
    2. Ask the sponsor to approve the initial budget
    3. Meet with representatives to clarify the service needs
    4. Assign each office a delivery date
    Show answer and explanation

    Answer: C. Meet with representatives to clarify the service needs

    Clarifying service needs with representatives establishes what the project must address before detailed planning. This supports Process, Task 1: Develop an integrated project management plan and plan delivery.

    Why the others are wrong

    • Estimate the schedule using a similar project: A similar project's schedule may not reflect these needs.
    • Ask the sponsor to approve the initial budget: Approving a budget before clarifying needs risks an inadequate estimate.
    • Assign each office a delivery date: Setting delivery dates before understanding the work is premature.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 1: Develop an integrated project management plan and plan delivery

  2. Integrated plan2. A software team expects customer needs to change and can release usable features frequently for feedback. The sponsor asks the project manager to recommend a development approach. Which approach best fits the project?
    1. Adaptive/agile, with iterative delivery and feedback
    2. Predictive, with scope fixed before delivery
    3. Predictive, with changes deferred until closure
    4. Hybrid, with all features specified before work begins
    Show answer and explanation

    Answer: A. Adaptive/agile, with iterative delivery and feedback

    An adaptive/agile approach supports frequent feedback and adjustment as customer needs evolve. This applies Process, Task 1: Develop an integrated project management plan and plan delivery.

    Why the others are wrong

    • Predictive, with scope fixed before delivery: Fixing scope early limits adaptation to changing needs.
    • Predictive, with changes deferred until closure: Deferring changes until closure delays response to feedback.
    • Hybrid, with all features specified before work begins: Specifying all features up front limits adaptation despite the hybrid label.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 1: Develop an integrated project management plan and plan delivery

  3. Integrated plan3. A predictive construction project must report its energy use during operations. The project manager is planning what information to collect. Which information is most useful for this requirement?
    1. The number of workers assigned to each construction activity
    2. The purchase price of the construction equipment
    3. The estimated energy consumption of the completed facility
    4. The number of inspections planned during construction
    Show answer and explanation

    Answer: C. The estimated energy consumption of the completed facility

    The estimated operational energy consumption directly supports the required sustainability reporting. Identifying information needed for project decisions is part of Process, Task 1: Develop an integrated project management plan and plan delivery.

    Why the others are wrong

    • The number of workers assigned to each construction activity: Staffing counts do not show the facility's operational energy use.
    • The purchase price of the construction equipment: Equipment purchase prices do not measure the facility's energy consumption.
    • The number of inspections planned during construction: Inspection counts do not show the facility's operational energy use.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 1: Develop an integrated project management plan and plan delivery

  4. Integrated plan4. A hybrid product team will release features in stages. Leaders need to decide whether each release delivers enough value to justify further investment, but no measures are agreed. What should the project manager do next?
    1. Ask the team to increase the number of features in each release
    2. Agree with stakeholders on value measures and required data
    3. Delay all releases until the complete product has been built
    4. Report completed work without defining measures of value
    Show answer and explanation

    Answer: B. Agree with stakeholders on value measures and required data

    Agreed value measures and supporting data give leaders a basis for investment decisions after each release. Determining critical information requirements is part of Process, Task 1: Develop an integrated project management plan and plan delivery.

    Why the others are wrong

    • Ask the team to increase the number of features in each release: More features do not necessarily demonstrate more value.
    • Delay all releases until the complete product has been built: Delaying releases prevents leaders from evaluating incremental results.
    • Report completed work without defining measures of value: Completed work alone may not show whether the release delivers value.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 1: Develop an integrated project management plan and plan delivery

Sign up free

Other PMP topics

GoConqr Original. Practice questions written with AI from the PMI 2026 PMP Examination Content Outline and settled project-management practice, each checked by a separate AI review. They are single- and multiple-response only: case sets, drag-and-drop, hotspot and pull-down items are not reproduced. Think a question is wrong? Use "Report" under it.

Independent study resource. Not affiliated with PMI. PMP and PMI are marks of the Project Management Institute.

© Visual Maths Resources Ltd

Feedback

What is it about?