PMP practice questions: Plan and manage resources
Planning, acquiring and managing the people and materials the project needs.
Updated 17 November 2026 for the 2026 PMP exam content outline
Key facts
Identify the people, skills, equipment, materials, facilities, and other resources needed to meet project requirements.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 4: Plan and manage resources
Estimate resource quantities and timing from the planned work, delivery approach, and relevant constraints.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 4: Plan and manage resources
Define resource roles and responsibilities and agree on how resources will be acquired, managed, and released.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 4: Plan and manage resources
Check resource availability and obtain commitments from resource owners before relying on assignments.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 4: Plan and manage resources
Account for resource costs, lead times, capacity, and availability when developing the project plan.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 4: Plan and manage resources
Compare resource demand with available capacity throughout the project and address shortages or overallocations.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 4: Plan and manage resources
Resource leveling adjusts work to address resource constraints and may extend the project schedule.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 4: Plan and manage resources
Resource smoothing adjusts activities within available schedule flexibility without changing the critical path or completion date.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 4: Plan and manage resources
In adaptive work, use the team's available capacity to select a sustainable amount of work for each iteration.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 4: Plan and manage resources
Reassess resource needs as requirements and priorities change, and coordinate any resulting plan changes with affected stakeholders.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 4: Plan and manage resources
Sample questions
1. A construction project is developing a predictive plan. The team has identified the work required for each deliverable but has not estimated resource needs. What should the project manager do next?
- Determine the people, equipment, and materials needed for the work.
- Assign available staff equally across all deliverables.
- Ask the sponsor to approve the final project budget.
- Set the schedule baseline before identifying resource needs.
Answer: A. Determine the people, equipment, and materials needed for the work.
The project manager should use the work requirements to identify the types of resources needed. This supports a realistic resource plan before commitments are made. Process, Task 4: Plan and manage resources.
- Assign available staff equally across all deliverables: Equal assignments may not match the needs of each deliverable.
- Ask the sponsor to approve the final project budget: Budget approval should follow development of resource estimates.
- Set the schedule baseline before identifying resource needs: A schedule baseline may be unrealistic without resource needs.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 4: Plan and manage resources
2. A predictive testing plan requires 240 hours of specialist work. Each specialist can provide 40 hours during the planned testing period. How many specialists are needed to complete the work in that period?
- 4 specialists
- 5 specialists
- 6 specialists
- 8 specialists
Answer: C. 6 specialists
Divide the required work by each specialist's available hours: 240 ÷ 40 = 6 specialists. This estimate assumes the work can be divided among them during the period. Process, Task 4: Plan and manage resources.
- 4 specialists: Four specialists provide only 160 hours.
- 5 specialists: Five specialists provide only 200 hours.
- 8 specialists: Eight specialists provide more than the stated requirement.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 4: Plan and manage resources
3. A hybrid healthcare project requires a specialist skill for an upcoming integration. The project manager finds that no current team member has that skill. What should the project manager do next?
- Assign the integration to any available team member.
- Assess options to obtain or develop the required skill.
- Remove the integration from the project scope.
- Escalate immediately and stop all project work.
Answer: B. Assess options to obtain or develop the required skill.
The project manager should assess feasible ways to address the skill gap, such as obtaining expertise or developing it within the team. The choice should support the integration requirement and the project's constraints. Process, Task 4: Plan and manage resources.
- Assign the integration to any available team member: Availability alone does not address the skill gap.
- Remove the integration from the project scope: Removing required scope without analysis or approval is premature.
- Escalate immediately and stop all project work: Escalation and a complete work stoppage are not yet justified.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 4: Plan and manage resources
4. A product team plans short iterations and will need shared test equipment for several features. Before requesting the equipment, what should the project manager determine? Choose two.
- The final cost of every future feature
- The testing needs of the planned features
- The dates or iterations when equipment is needed
- The names of all future project sponsors
- The closing date for the entire project
Answer: B. The testing needs of the planned features, C. The dates or iterations when equipment is needed
The features' testing needs and timing indicate what equipment to request and when. Planning both supports the team's delivery requirements. Process, Task 4: Plan and manage resources.
- The final cost of every future feature: Final costs for every future feature are not needed to identify testing equipment.
- The names of all future project sponsors: Future sponsor names do not establish equipment requirements.
- The closing date for the entire project: The overall closing date does not identify when testing equipment is needed.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 4: Plan and manage resources