PMP practice questions: Develop and manage project scope
Defining what is in and out of the project and controlling it as work proceeds.
Updated 17 November 2026 for the 2026 PMP exam content outline
Key facts
Define project scope by identifying the work needed to deliver the agreed product, service, or result.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 2: Develop and manage project scope
Distinguish product scope, which describes the features and functions of the deliverable, from project scope, which describes the work required to deliver it.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 2: Develop and manage project scope
Define deliverables, boundaries, exclusions, and acceptance criteria so stakeholders share a clear understanding of the scope.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 2: Develop and manage project scope
Trace scope to stakeholder requirements and project objectives to support alignment and identify gaps.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 2: Develop and manage project scope
Engage relevant stakeholders to resolve scope differences and obtain agreement from those authorized to approve it.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 2: Develop and manage project scope
Document agreed scope and acceptance criteria in artifacts appropriate to the project approach.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 2: Develop and manage project scope
In predictive work, decompose deliverables into a work breakdown structure until the work can be estimated, assigned, and managed.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 2: Develop and manage project scope
Ensure the work breakdown structure includes all the project work without duplicating work across its components.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 2: Develop and manage project scope
In adaptive/agile work, refine and break down backlog items as understanding improves so the team can deliver usable increments.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 2: Develop and manage project scope
Manage proposed scope changes through the project's agreed process, assessing impacts and obtaining required authorization before incorporating them.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 2: Develop and manage project scope
Sample questions
1. A healthcare project must deliver a patient scheduling system. Stakeholders describe the desired system as 'easy to use' but have not explained what that means. What should the project manager do next?
- Set a delivery date based on the current description
- Ask the team to select a design without stakeholder input
- Work with stakeholders to clarify the expected user needs
- Treat ease of use as outside the project scope
Answer: C. Work with stakeholders to clarify the expected user needs
Clarifying user needs makes the intended scope more understandable and reduces conflicting assumptions. This supports Process, Task 2: Develop and manage project scope.
- Set a delivery date based on the current description: A date does not resolve the ambiguity in the desired outcome.
- Ask the team to select a design without stakeholder input: A design selected without clarification may not meet user needs.
- Treat ease of use as outside the project scope: Excluding the need without discussion could omit an important expectation.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 2: Develop and manage project scope
2. A public-sector team is defining the scope of a predictive project to replace a service counter. The proposed scope lists the deliverable but not how stakeholders will judge it acceptable. What should the project manager do next?
- Ask the team to begin work using its own assumptions
- Set the final acceptance decision aside until project closure
- Request a baseline change before defining the criteria
- Develop clear acceptance criteria with the relevant stakeholders
Answer: D. Develop clear acceptance criteria with the relevant stakeholders
Clear acceptance criteria help stakeholders and the team understand what the deliverable must satisfy. This supports Process, Task 2: Develop and manage project scope.
- Ask the team to begin work using its own assumptions: The team's assumptions may differ from stakeholder expectations.
- Set the final acceptance decision aside until project closure: Waiting until closure risks discovering disagreements too late.
- Request a baseline change before defining the criteria: A baseline change is premature when the criteria are still being defined.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 2: Develop and manage project scope
3. A hybrid product launch has a fixed release date, but stakeholders have proposed more features than the team expects to deliver. What should the project manager do next to define a feasible release scope?
- Commit to every proposed feature and shorten testing
- Work with stakeholders to prioritize features against the release constraints
- Ask the team to select features without stakeholder input
- Move the release date without consulting the sponsor
Answer: B. Work with stakeholders to prioritize features against the release constraints
Prioritizing features with stakeholders helps define a release scope that reflects value and the fixed date. This supports Process, Task 2: Develop and manage project scope.
- Commit to every proposed feature and shorten testing: Committing to everything without analysis can put quality and delivery at risk.
- Ask the team to select features without stakeholder input: The team needs stakeholder input to understand feature value.
- Move the release date without consulting the sponsor: Changing the date without consultation ignores the stated constraint.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 2: Develop and manage project scope
4. A project manager is planning a predictive hospital renovation. Stakeholders disagree about whether replacing furniture is part of the project. What should the project manager do next to define the scope?
- Ask the contractor to include furniture in its estimate.
- Add furniture replacement to the schedule baseline.
- Escalate the disagreement directly to the steering committee.
- Clarify the project's deliverables and exclusions with stakeholders.
Answer: D. Clarify the project's deliverables and exclusions with stakeholders.
Clarifying deliverables and exclusions helps establish what the project will and will not include. This supports Process, Task 2: Develop and manage project scope.
- Ask the contractor to include furniture in its estimate: An estimate does not resolve whether furniture is in scope.
- Add furniture replacement to the schedule baseline: The schedule should reflect an understood scope, not settle the disagreement.
- Escalate the disagreement directly to the steering committee: Escalation is premature before discussing the boundaries with stakeholders.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 2: Develop and manage project scope