PMP practice questions: Develop and manage project scope

Defining what is in and out of the project and controlling it as work proceeds.

13 questions · 10 key rules

Updated 17 November 2026 for the 2026 PMP exam content outline

Key facts

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Scope1. A healthcare project must deliver a patient scheduling system. Stakeholders describe the desired system as 'easy to use' but have not explained what that means. What should the project manager do next?
    1. Set a delivery date based on the current description
    2. Ask the team to select a design without stakeholder input
    3. Work with stakeholders to clarify the expected user needs
    4. Treat ease of use as outside the project scope
    Show answer and explanation

    Answer: C. Work with stakeholders to clarify the expected user needs

    Clarifying user needs makes the intended scope more understandable and reduces conflicting assumptions. This supports Process, Task 2: Develop and manage project scope.

    Why the others are wrong

    • Set a delivery date based on the current description: A date does not resolve the ambiguity in the desired outcome.
    • Ask the team to select a design without stakeholder input: A design selected without clarification may not meet user needs.
    • Treat ease of use as outside the project scope: Excluding the need without discussion could omit an important expectation.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 2: Develop and manage project scope

  2. Scope2. A public-sector team is defining the scope of a predictive project to replace a service counter. The proposed scope lists the deliverable but not how stakeholders will judge it acceptable. What should the project manager do next?
    1. Ask the team to begin work using its own assumptions
    2. Set the final acceptance decision aside until project closure
    3. Request a baseline change before defining the criteria
    4. Develop clear acceptance criteria with the relevant stakeholders
    Show answer and explanation

    Answer: D. Develop clear acceptance criteria with the relevant stakeholders

    Clear acceptance criteria help stakeholders and the team understand what the deliverable must satisfy. This supports Process, Task 2: Develop and manage project scope.

    Why the others are wrong

    • Ask the team to begin work using its own assumptions: The team's assumptions may differ from stakeholder expectations.
    • Set the final acceptance decision aside until project closure: Waiting until closure risks discovering disagreements too late.
    • Request a baseline change before defining the criteria: A baseline change is premature when the criteria are still being defined.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 2: Develop and manage project scope

  3. Scope3. A hybrid product launch has a fixed release date, but stakeholders have proposed more features than the team expects to deliver. What should the project manager do next to define a feasible release scope?
    1. Commit to every proposed feature and shorten testing
    2. Work with stakeholders to prioritize features against the release constraints
    3. Ask the team to select features without stakeholder input
    4. Move the release date without consulting the sponsor
    Show answer and explanation

    Answer: B. Work with stakeholders to prioritize features against the release constraints

    Prioritizing features with stakeholders helps define a release scope that reflects value and the fixed date. This supports Process, Task 2: Develop and manage project scope.

    Why the others are wrong

    • Commit to every proposed feature and shorten testing: Committing to everything without analysis can put quality and delivery at risk.
    • Ask the team to select features without stakeholder input: The team needs stakeholder input to understand feature value.
    • Move the release date without consulting the sponsor: Changing the date without consultation ignores the stated constraint.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 2: Develop and manage project scope

  4. Scope4. A project manager is planning a predictive hospital renovation. Stakeholders disagree about whether replacing furniture is part of the project. What should the project manager do next to define the scope?
    1. Ask the contractor to include furniture in its estimate.
    2. Add furniture replacement to the schedule baseline.
    3. Escalate the disagreement directly to the steering committee.
    4. Clarify the project's deliverables and exclusions with stakeholders.
    Show answer and explanation

    Answer: D. Clarify the project's deliverables and exclusions with stakeholders.

    Clarifying deliverables and exclusions helps establish what the project will and will not include. This supports Process, Task 2: Develop and manage project scope.

    Why the others are wrong

    • Ask the contractor to include furniture in its estimate: An estimate does not resolve whether furniture is in scope.
    • Add furniture replacement to the schedule baseline: The schedule should reflect an understood scope, not settle the disagreement.
    • Escalate the disagreement directly to the steering committee: Escalation is premature before discussing the boundaries with stakeholders.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 2: Develop and manage project scope

Sign up free

Other PMP topics

GoConqr Original. Practice questions written with AI from the PMI 2026 PMP Examination Content Outline and settled project-management practice, each checked by a separate AI review. They are single- and multiple-response only: case sets, drag-and-drop, hotspot and pull-down items are not reproduced. Think a question is wrong? Use "Report" under it.

Independent study resource. Not affiliated with PMI. PMP and PMI are marks of the Project Management Institute.

© Visual Maths Resources Ltd

Feedback

What is it about?