PMP practice questions: Manage project closure

Closing the project or phase properly and handing over what was delivered.

14 questions · 10 key rules

Updated 17 November 2026 for the 2026 PMP exam content outline

Key facts

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Project closure1. A predictive construction project has completed its planned work. The project manager has not yet obtained approval of project completion from the responsible stakeholders. What should the project manager do next?
    1. Archive the project records and announce closure
    2. Release the team and close the project accounts
    3. Move the remaining review to the operations team
    4. Seek completion approval from the responsible stakeholders
    Show answer and explanation

    Answer: D. Seek completion approval from the responsible stakeholders

    The project manager should obtain stakeholder approval before treating project completion as approved. This supports Process, Task 10: Manage project closure.

    Why the others are wrong

    • Archive the project records and announce closure: Archiving and announcing closure do not establish stakeholder approval.
    • Release the team and close the project accounts: Releasing resources and closing accounts do not replace approval.
    • Move the remaining review to the operations team: Operations may participate in transition, but that does not replace stakeholder approval.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 10: Manage project closure

  2. Project closure2. A hybrid product project is ready for closure, but several stakeholder groups participated in delivery. The project manager is unsure who can approve completion. What should the project manager do next?
    1. Ask every team member to vote on completion
    2. Request approval from the largest stakeholder group
    3. Review the agreed approval arrangements with stakeholders
    4. Treat delivery of the final increment as approval
    Show answer and explanation

    Answer: C. Review the agreed approval arrangements with stakeholders

    Reviewing the agreed arrangements helps identify the stakeholders responsible for approving completion. Process, Task 10: Manage project closure includes obtaining that approval.

    Why the others are wrong

    • Ask every team member to vote on completion: A team vote does not establish who has approval authority.
    • Request approval from the largest stakeholder group: The largest group is not necessarily authorized to approve completion.
    • Treat delivery of the final increment as approval: Delivering an increment does not itself establish completion approval.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 10: Manage project closure

  3. Project closure3. At a hybrid healthcare project's completion review, a stakeholder authorized to approve closure identifies an unresolved requirement. The team believes the concern is minor. What should the project manager do next?
    1. Record the concern and announce that the project is complete
    2. Review the concern against agreed completion criteria with the stakeholder
    3. Ask the team to remove the requirement from the scope
    4. Escalate immediately and request that the sponsor override the stakeholder
    Show answer and explanation

    Answer: B. Review the concern against agreed completion criteria with the stakeholder

    Reviewing the concern against the agreed criteria helps establish whether the project is ready for approval and what remains unresolved. This supports Process, Task 10: Manage project closure.

    Why the others are wrong

    • Record the concern and announce that the project is complete: Recording the concern does not resolve its effect on approval.
    • Ask the team to remove the requirement from the scope: The team should not unilaterally remove an agreed requirement.
    • Escalate immediately and request that the sponsor override the stakeholder: Escalation is premature before the concern has been assessed.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 10: Manage project closure

  4. Project closure4. A predictive public-sector project has received verbal completion approval from its authorized stakeholder. The agreed closure procedure calls for documented approval. What should the project manager do next?
    1. Ask the delivery team to document its own acceptance
    2. Document the approval using the agreed closure procedure
    3. Close the project because verbal approval was received
    4. Request a new approval from every project stakeholder
    Show answer and explanation

    Answer: B. Document the approval using the agreed closure procedure

    Documenting the approval follows the project's agreed closure procedure and preserves a record of the decision. This supports Process, Task 10: Manage project closure.

    Why the others are wrong

    • Ask the delivery team to document its own acceptance: Team acceptance is not a substitute for the authorized stakeholder's approval.
    • Close the project because verbal approval was received: Closing without the agreed documentation leaves the procedure incomplete.
    • Request a new approval from every project stakeholder: Approval from every stakeholder may not be required by the agreed procedure.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 10: Manage project closure

Sign up free

Other PMP topics

GoConqr Original. Practice questions written with AI from the PMI 2026 PMP Examination Content Outline and settled project-management practice, each checked by a separate AI review. They are single- and multiple-response only: case sets, drag-and-drop, hotspot and pull-down items are not reproduced. Think a question is wrong? Use "Report" under it.