PMP practice questions: Plan and manage procurement
Planning purchases and managing the suppliers and contracts behind them.
Updated 17 November 2026 for the 2026 PMP exam content outline
Key facts
Use make-or-buy analysis to decide which products or services to obtain externally, considering capability, cost, schedule, and risk.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 5: Plan and manage procurement
Develop a procurement strategy and delivery solution that align supplier responsibilities, timing, and acceptance criteria with the project approach and desired outcomes.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 5: Plan and manage procurement
Plan procurement activities, evaluation criteria, approvals, and supplier oversight before soliciting offers.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 5: Plan and manage procurement
Select contract types according to scope certainty and risk allocation: fixed-price contracts generally place more cost risk on the seller than cost-reimbursable contracts.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 5: Plan and manage procurement
Time-and-materials contracts pay for agreed labor rates and materials, making cost monitoring important when the total effort is uncertain.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 5: Plan and manage procurement
Execute the procurement management plan by soliciting offers, evaluating them against established criteria, and obtaining required approvals before award.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 5: Plan and manage procurement
Determine a negotiation strategy by establishing objectives, priorities, constraints, and acceptable alternatives before discussions.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 5: Plan and manage procurement
Participate in negotiations to clarify scope, price, responsibilities, delivery, acceptance, and change terms with authorized procurement personnel.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 5: Plan and manage procurement
Manage suppliers against the agreement and process contract changes through the authorized change procedure.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 5: Plan and manage procurement
Evaluate vendor performance against agreed measures, address deviations, and document relevant results.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 5: Plan and manage procurement
Verify that deliverables and procurement objectives meet contractual acceptance criteria before formal acceptance and contract closeout.
PMI, Project Management Professional Examination Content Outline - 2026, Domain II Process, Task 5: Plan and manage procurement
Sample questions
1. A predictive construction project needs a specialized inspection service. Before seeking suppliers, the project manager discovers that an internal team may be able to perform the work. What should the project manager do next?
- Ask a preferred supplier to begin the inspection
- Add the supplier’s price to the project baseline
- Escalate the sourcing decision to the sponsor
- Compare internal and external options for the service
Answer: D. Compare internal and external options for the service
The project manager should assess whether to perform the service internally or obtain it externally before starting procurement. This supports an informed sourcing decision under Process, Task 5: Plan and manage procurement.
- Ask a preferred supplier to begin the inspection: Starting supplier work skips the sourcing assessment.
- Add the supplier’s price to the project baseline: A supplier price alone does not establish the preferred sourcing option.
- Escalate the sourcing decision to the sponsor: Escalation is premature before the options have been assessed.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 5: Plan and manage procurement
2. A hybrid healthcare project plans to procure a data-migration service. The team is preparing to request supplier proposals, but stakeholders have not agreed on the required outcomes. What should the project manager do next?
- Work with stakeholders to define the required outcomes
- Request proposals and let suppliers define the outcomes
- Select a supplier using past performance alone
- Delay the decision until migration work has started
Answer: A. Work with stakeholders to define the required outcomes
Defining the required outcomes helps suppliers prepare relevant proposals and gives the team a basis for evaluating them. This is part of procurement planning under Process, Task 5: Plan and manage procurement.
- Request proposals and let suppliers define the outcomes: Supplier proposals cannot replace agreement on the project’s needs.
- Select a supplier using past performance alone: Past performance alone does not establish whether a supplier can meet the requirements.
- Delay the decision until migration work has started: Starting migration without agreed outcomes risks misaligned work.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 5: Plan and manage procurement
3. A predictive construction project has received bids for equipment. The procurement management plan specifies weighted evaluation criteria, including price and delivery capability. What should the project manager do next?
- Select the bidder with the lowest price immediately.
- Ask the sponsor to select a preferred bidder.
- Evaluate the bids using the agreed weighted criteria.
- Revise the criteria to favor the earliest delivery.
Answer: C. Evaluate the bids using the agreed weighted criteria.
The agreed criteria provide a consistent basis for evaluating the bids. This applies Process, Task 5: Plan and manage procurement.
- Select the bidder with the lowest price immediately: Lowest price alone ignores the other agreed criteria.
- Ask the sponsor to select a preferred bidder: A sponsor's preference does not replace the agreed evaluation.
- Revise the criteria to favor the earliest delivery: Changing criteria after receiving bids undermines a consistent evaluation.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 5: Plan and manage procurement
4. On a hybrid project, a supplier proposes a feature that would change the contracted deliverables and price. The procurement management plan specifies an approval process for contract changes. What should the project manager do next?
- Ask the supplier to begin work while approval is pending.
- Update the contract price to match the supplier's proposal.
- Reject the feature because the contract is already signed.
- Assess the proposal and follow the agreed change process.
Answer: D. Assess the proposal and follow the agreed change process.
The project manager should assess the proposed change before seeking approval through the agreed process. This applies Process, Task 5: Plan and manage procurement.
- Ask the supplier to begin work while approval is pending: Starting work before approval can create an unauthorized commitment.
- Update the contract price to match the supplier's proposal: The contract price should not be changed without required approval.
- Reject the feature because the contract is already signed: A signed contract can be changed through an agreed process.
Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 5: Plan and manage procurement