PMP practice questions: Plan and manage procurement

Planning purchases and managing the suppliers and contracts behind them.

13 questions · 11 key rules

Updated 17 November 2026 for the 2026 PMP exam content outline

Key facts

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Procurement1. A predictive construction project needs a specialized inspection service. Before seeking suppliers, the project manager discovers that an internal team may be able to perform the work. What should the project manager do next?
    1. Ask a preferred supplier to begin the inspection
    2. Add the supplier’s price to the project baseline
    3. Escalate the sourcing decision to the sponsor
    4. Compare internal and external options for the service
    Show answer and explanation

    Answer: D. Compare internal and external options for the service

    The project manager should assess whether to perform the service internally or obtain it externally before starting procurement. This supports an informed sourcing decision under Process, Task 5: Plan and manage procurement.

    Why the others are wrong

    • Ask a preferred supplier to begin the inspection: Starting supplier work skips the sourcing assessment.
    • Add the supplier’s price to the project baseline: A supplier price alone does not establish the preferred sourcing option.
    • Escalate the sourcing decision to the sponsor: Escalation is premature before the options have been assessed.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 5: Plan and manage procurement

  2. Procurement2. A hybrid healthcare project plans to procure a data-migration service. The team is preparing to request supplier proposals, but stakeholders have not agreed on the required outcomes. What should the project manager do next?
    1. Work with stakeholders to define the required outcomes
    2. Request proposals and let suppliers define the outcomes
    3. Select a supplier using past performance alone
    4. Delay the decision until migration work has started
    Show answer and explanation

    Answer: A. Work with stakeholders to define the required outcomes

    Defining the required outcomes helps suppliers prepare relevant proposals and gives the team a basis for evaluating them. This is part of procurement planning under Process, Task 5: Plan and manage procurement.

    Why the others are wrong

    • Request proposals and let suppliers define the outcomes: Supplier proposals cannot replace agreement on the project’s needs.
    • Select a supplier using past performance alone: Past performance alone does not establish whether a supplier can meet the requirements.
    • Delay the decision until migration work has started: Starting migration without agreed outcomes risks misaligned work.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 5: Plan and manage procurement

  3. Procurement3. A predictive construction project has received bids for equipment. The procurement management plan specifies weighted evaluation criteria, including price and delivery capability. What should the project manager do next?
    1. Select the bidder with the lowest price immediately.
    2. Ask the sponsor to select a preferred bidder.
    3. Evaluate the bids using the agreed weighted criteria.
    4. Revise the criteria to favor the earliest delivery.
    Show answer and explanation

    Answer: C. Evaluate the bids using the agreed weighted criteria.

    The agreed criteria provide a consistent basis for evaluating the bids. This applies Process, Task 5: Plan and manage procurement.

    Why the others are wrong

    • Select the bidder with the lowest price immediately: Lowest price alone ignores the other agreed criteria.
    • Ask the sponsor to select a preferred bidder: A sponsor's preference does not replace the agreed evaluation.
    • Revise the criteria to favor the earliest delivery: Changing criteria after receiving bids undermines a consistent evaluation.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 5: Plan and manage procurement

  4. Procurement4. On a hybrid project, a supplier proposes a feature that would change the contracted deliverables and price. The procurement management plan specifies an approval process for contract changes. What should the project manager do next?
    1. Ask the supplier to begin work while approval is pending.
    2. Update the contract price to match the supplier's proposal.
    3. Reject the feature because the contract is already signed.
    4. Assess the proposal and follow the agreed change process.
    Show answer and explanation

    Answer: D. Assess the proposal and follow the agreed change process.

    The project manager should assess the proposed change before seeking approval through the agreed process. This applies Process, Task 5: Plan and manage procurement.

    Why the others are wrong

    • Ask the supplier to begin work while approval is pending: Starting work before approval can create an unauthorized commitment.
    • Update the contract price to match the supplier's proposal: The contract price should not be changed without required approval.
    • Reject the feature because the contract is already signed: A signed contract can be changed through an agreed process.

    Source: PMI, PMP Examination Content Outline - 2026: task statements and enablers; standard project-management…, Domain II Process, Task 5: Plan and manage procurement

Sign up free

Other PMP topics

GoConqr Original. Practice questions written with AI from the PMI 2026 PMP Examination Content Outline and settled project-management practice, each checked by a separate AI review. They are single- and multiple-response only: case sets, drag-and-drop, hotspot and pull-down items are not reproduced. Think a question is wrong? Use "Report" under it.

Independent study resource. Not affiliated with PMI. PMP and PMI are marks of the Project Management Institute.